PRJ-2026-028On track4ExecutionWaterfall

SCA Strategy Refresh & Execution Plans

Add to watchlist

Turning the four axes and 34 initiatives of the SCA strategy into portfolios, initiatives and KPIs aligned with Saudi Vision 2030.

Budget (BAC)

SAR 3.2M

Actual cost

SAR 2.2M

⁦70%⁩ of budget

Progress

⁦70%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 3.2M

SPI · CPI

1.03Schedule performance index · 1.031.00Cost performance index · 1.00

Forecast finish

⁦2026-12-15⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure27 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 March 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 May 2026Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate8 June 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate27 November 2026Closure · Not startedClosure · Not started

Team & roles

3 members, about ⁦1.1⁩ full-time equivalents

Leadership

3 members

  • Abeer H. Al-ShamraniProject manager⁦70%⁩A
  • Dr. Mohammed I. Al-SubaieProject sponsor⁦25%⁩R
  • Dr. Noura M. Al-OtaibiGovernance adviser to the strategy refresh⁦10%⁩Allocated ⁦105%⁩ across all projectsR

A AccountableR ResponsibleC ConsultedI Informed

Stakeholders

⁦6⁩ stakeholders, ⁦5⁩ of them below the engagement needed

Power / interest matrix

Pick one to see how they are handled

Power & influence

Keep satisfied1

high power, lower interest

Manage closely4

high power and interest

Monitor0

minimal effort

Keep informed1

high interest, lower power

Dr. Mohammed I. Al-SubaieManage closelyDr. Amal F. Al-SudairiManage closelyProject Management Office (PMO)Manage closelyEnd beneficiariesKeep informedGeneral Directorate of Financial AffairsKeep satisfiedDar Al-Mashura Management ConsultingManage closely

Interest

Project sponsor

Dr. Mohammed I. Al-Subaie

Decisions and funding

Influence

Interest

Engagement level

Unaware

Resistant

Neutral

Now

Supportive

Target

Leading

A gap of ⁦1⁩ step — needs an engagement plan.

Impact on the project
Approves gates and changes
Engagement plan
Monthly briefing
Last contact⁦2026-10-21⁩
⁦6⁩ results
Export CSV
OrganisationRoleActions
Dr. Mohammed I. Al-SubaieProject sponsorDecisions and fundingSupportiveLeadingAbeer H. Al-ShamraniAbeer H. Al-ShamraniHead of Strategy ManagementP-039a.alshamrani@sca.sa⁦2026-10-21⁩
Dr. Amal F. Al-SudairiProject ownerAccepts deliverables, owns benefitsSupportiveLeadingAbeer H. Al-ShamraniAbeer H. Al-ShamraniHead of Strategy ManagementP-039a.alshamrani@sca.sa⁦2026-10-24⁩
Project Management Office (PMO)GovernanceCompliance and data qualitySupportiveAbeer H. Al-ShamraniAbeer H. Al-ShamraniHead of Strategy ManagementP-039a.alshamrani@sca.sa⁦2026-10-18⁩
General Directorate of Financial AffairsInternal departmentPayment approvalNeutralSupportiveHaifa S. Al-RuwailiHaifa S. Al-RuwailiSenior Financial AnalystP-037h.alruwaili@sca.sa⁦2026-10-15⁩
Dar Al-Mashura Management ConsultingMain vendorDelivers the contracted workNeutralSupportiveAbeer H. Al-ShamraniAbeer H. Al-ShamraniHead of Strategy ManagementP-039a.alshamrani@sca.sa⁦2026-10-25⁩
End beneficiariesBeneficiariesUsers of the outcomeNeutralSupportiveAbeer H. Al-ShamraniAbeer H. Al-ShamraniHead of Strategy ManagementP-039a.alshamrani@sca.sa⁦2026-09-27⁩
⁦1⁩–⁦6⁩ of ⁦6⁩

Communication plan

Who needs what, when, through which channel, and who owns it.

  • Project sponsorStatus and decisions neededMonthlyMeetingAbeer H. Al-Shamrani⁦2026-11-16⁩
  • Project ownerDeliverable status and acceptance datesFortnightlyEmailAbeer H. Al-Shamrani⁦2026-11-04⁩
  • PMOData and indicator updatesWeeklyDashboardAbeer H. Al-Shamrani⁦2026-11-01⁩
  • BeneficiariesWhat changes and whenAt milestonesNewsletterAbeer H. Al-ShamraniAt launch

Coming up

By date

  1. 012026-11PMODashboard · Weekly
  2. 042026-11Project ownerEmail · Fortnightly
  3. 162026-11Project sponsorMeeting · Monthly