PRJ-2026-028On track4ExecutionWaterfall

SCA Strategy Refresh & Execution Plans

Add to watchlist

Turning the four axes and 34 initiatives of the SCA strategy into portfolios, initiatives and KPIs aligned with Saudi Vision 2030.

Budget (BAC)

SAR 3.2M

Actual cost

SAR 2.2M

⁦70%⁩ of budget

Progress

⁦70%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 3.2M

SPI · CPI

1.03Schedule performance index · 1.031.00Cost performance index · 1.00

Forecast finish

⁦2026-12-15⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure27 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 March 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 May 2026Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate8 June 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate27 November 2026Closure · Not startedClosure · Not started

Priority evaluation

Criteria, weights and the P1–P4 result

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Priority evaluation

Criteria, weights and the P1–P4 result

Form no.
SCA-PMO-F02
Template edition
1.3
Version
V4
Form date
⁦2025-11-29⁩
Hijri
8 Jumada II 1447 AH
ApprovedPRJ-2026-028SCA Strategy Refresh & Execution Plans

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-028
Project
SCA Strategy Refresh & Execution Plans
Portfolio
Institutional Excellence & Governance Portfolio
Sector
Strategy & Institutional Excellence Sector
Sponsor
Dr. Mohammed I. Al-Subaie
Project manager
Abeer H. Al-Shamrani

1The resultAuto-filled

Priority score

82 of 100

Class

P1

75–100

Priority model

Version 4

Class thresholdsAuto-filled

P1 from 75 · P2 from 60 · P3 from 45 · P4 below 45

2Criteria and weightsAuto-filled

Rated 1–5; the cost criteria (risk, complexity, resources) are turned around before weighting.

CriterionWeightRatingPoints
Fit with the SCA strategy⁦20%⁩5.020.0
Value added to the contracting sector⁦12%⁩5.012.0
Financial return & sustainability⁦8%⁩5.08.0
Urgency⁦10%⁩4.89.5
Regulatory requirement⁦10%⁩1.61.5
Risk⁦7%⁩1.07.0
Complexity⁦6%⁩1.06.0
Resource requirement⁦5%⁩1.05.0
Impact on contractors & beneficiaries⁦14%⁩3.79.4
Sustainability impact⁦3%⁩2.00.8
Digital transformation impact⁦5%⁩2.92.4
Total⁦100%⁩—82

Approval logChain: Priority evaluation approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Ghada A. Al-ShahraniDirector, Qualification Programmes & CapabilitySubmitted—⁦2025-11-29⁩ 13:52
2Evaluation checked against the modelMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2025-11-30⁩ 11:56
3Portfolio manager reviewTechnical acceptanceDr. Noura M. Al-OtaibiPortfolio managerApproved—⁦2025-12-02⁩ 12:03
4Class approved — Project Approval CommitteeTechnical acceptanceDr. Noura M. Al-OtaibiProject Approval CommitteeApproved—⁦2025-12-03⁩ 13:10

Signatures

Evaluation checked against the model

Ghada A. Al-Shahrani

Approved⁦2025-11-30⁩

Portfolio manager review

Dr. Noura M. Al-Otaibi

Approved⁦2025-12-02⁩

Class approved — Project Approval Committee

Dr. Noura M. Al-Otaibi

Approved⁦2025-12-03⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F02 · version V4

Priority evaluation

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Priority evaluation approval · version ⁦1⁩

Submitted by Ghada A. Al-Shahrani on ⁦2025-11-29⁩

  1. Methodology review

    Evaluation checked against the model

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2025-11-30⁩ at ⁦11:56⁩

  2. Technical acceptance

    Portfolio manager review

    Dr. Noura M. Al-Otaibi · Portfolio manager

    Approved · ⁦2025-12-02⁩ at ⁦12:03⁩

  3. Technical acceptance

    Class approved — Project Approval Committee

    Dr. Noura M. Al-Otaibi · Project Approval Committee

    Approved · ⁦2025-12-03⁩ at ⁦13:10⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V4ApprovedCurrent⁦2025-11-29⁩

    Evaluated on the approved priority model

    Ghada A. Al-Shahrani

Only one version so far.