SCA Strategy Refresh & Execution Plans Subtask Last item under this branch 2026-12-15 70% SCA Strategy Refresh & Execution Plans Planned: 2026-05-03 → 2026-12-15 Forecast: 2026-05-03 → 2026-12-15 Float: 0d
1 Management & governance Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-07-12 100% Management & governance Planned: 2026-05-03 → 2026-06-27 Actual: 2026-05-03 → 2026-07-12
1.1 Project plan & baseline Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-06-15 100% Project plan & baseline Planned: 2026-05-03 → 2026-06-06 Actual: 2026-05-03 → 2026-06-15
1.2 Monitoring & reporting Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-07-12 100% Monitoring & reporting Planned: 2026-05-24 → 2026-06-27 Actual: 2026-05-30 → 2026-07-12
Project plan approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-07-12 100% Project plan approved Planned: 2026-06-27 → 2026-06-27 Actual: 2026-07-12 → 2026-07-12 Project plan approved
2 Diagnosis Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-09-04 100% Diagnosis Planned: 2026-06-15 → 2026-08-09 Actual: 2026-06-26 → 2026-09-04
2.1 Current-state assessment Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-08-08 100% Current-state assessment Planned: 2026-06-15 → 2026-07-19 Actual: 2026-06-26 → 2026-08-08
2.2 Benchmarking Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-09-04 100% Benchmarking Planned: 2026-07-06 → 2026-08-09 Actual: 2026-07-23 → 2026-09-04
Designs approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-09-04 100% Designs approved Planned: 2026-08-09 → 2026-08-09 Actual: 2026-09-04 → 2026-09-04 Designs approved
3 Design Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-10-26 100% Design Planned: 2026-07-27 → 2026-09-21 Actual: 2026-08-19 → 2026-10-26
3.1 Target model Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-10-01 100% Target model Planned: 2026-07-27 → 2026-08-30 Actual: 2026-08-19 → 2026-10-01
3.2 Roadmap Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-10-26 100% Roadmap Planned: 2026-08-18 → 2026-09-21 Actual: 2026-09-15 → 2026-10-26
Build complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-10-26 100% Build complete Planned: 2026-09-21 → 2026-09-21 Actual: 2026-10-26 → 2026-10-26 Build complete
4 Implementation Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-11-22 34% Implementation Planned: 2026-09-08 → 2026-11-02 Forecast: 2026-09-08 → 2026-11-22 Float: 1d
4.1 Wave 1 Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-11-11 67% Wave 1 Planned: 2026-09-08 → 2026-10-12 Forecast: 2026-09-08 → 2026-11-11 Float: 1d Drag to change its duration +30
4.2 Wave 2 Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-11-22 0% Wave 2 Planned: 2026-09-29 → 2026-11-02 Forecast: 2026-11-04 → 2026-11-22 Float: 1d Drag to change its dates +20
Testing & acceptance complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-11-22 0% Testing & acceptance complete Planned: 2026-11-02 → 2026-11-02 Forecast: 2026-11-22 → 2026-11-22 Float: 23d Drag to change its dates Testing & acceptance complete
5 Handover & knowledge transfer Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-12-15 0% Handover & knowledge transfer Planned: 2026-10-21 → 2026-12-15 Forecast: 2026-11-15 → 2026-12-15 Float: 0d
5.1 Knowledge transfer Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-12-03 0% Knowledge transfer Planned: 2026-10-21 → 2026-11-24 Forecast: 2026-11-15 → 2026-12-03 Float: 1d Drag to change its dates +9
5.2 Final report Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-12-14 0% Final report Planned: 2026-11-11 → 2026-12-15 Forecast: 2026-11-26 → 2026-12-14 Float: 1d Drag to change its dates
Final handover Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-12-15 0% Final handover Planned: 2026-12-15 → 2026-12-15 Forecast: 2026-12-15 → 2026-12-15 Float: 0d Drag to change its dates Final handover