Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-001Off track4ExecutionHybrid

SCA ERP System

Remove from watchlist

One integrated system for the Authority’s finance, procurement and HR, connected to the Etimad platform.

Early warning: ⁦86%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SAR 64.5M

Actual cost

SAR 44.7M

⁦69%⁩ of budget

Progress

⁦61%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 73.3M

SAR +8.8M

SPI · CPI

0.82Schedule performance index · 0.820.88Cost performance index · 0.88

Forecast finish

⁦2027-02-27⁩

58 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure4 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate13 November 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate12 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate7 May 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate4 November 2026Closure · Not startedClosure · Not started

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Form no.
SCA-PMO-F08
Template edition
1.1
Version
V1
Form date
⁦2026-04-12⁩
Hijri
24 Shawwal 1447 AH
ApprovedCRT-001-04Solution design

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-001
Project
SCA ERP System
Portfolio
Technology & Enterprise Systems Portfolio
Sector
Digital Transformation Sector
Sponsor
Sarah A. Al-Qarni
Project manager
Dana S. Al-Saleh

1The deliverableAuto-filled

DeliverableAuto-filled
Solution design
DescriptionAuto-filled
A contractual output tied to its WBS work package.
OwnerAuto-filled
Sarah A. Al-Qarni
VersionAuto-filled
V1
Weight in the projectAuto-filled
⁦10%⁩
DueAuto-filled
⁦2025-10-24⁩

2Evidence of completionAuto-filled

FileVersionByDate
PRJ-2026-001_2.2_v1.pdfV1Sarah A. Al-Qarni⁦2025-11-05⁩

3Inspection and acceptance criteria

CriterionResult
Matches the approved scope of workMet
Quality review with no major findingsMet
Evidence attached and signed by the ownerMet
Met3 of 3
InspectorAuto-filled
Munirah A. Al-Khalidi
Accepted byAuto-filled
Sarah A. Al-Qarni
Acceptance note
Inspected and accepted against the approved acceptance criteria.

4Financial linkAuto-filled

Contract milestoneAuto-filled
Designs approved
ContractAuto-filled
CTR-2025-003
Payment certificateAuto-filled
Linked when the certificate is raised
Payment against itAuto-filled
—

Approval logChain: Deliverable acceptance & certificate · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Sarah A. Al-QarniHead, Corporate Support SectorSubmitted—⁦2025-11-05⁩ 14:41
2Evidence against the acceptance criteriaMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2025-11-09⁩ 12:27
3Inspection & technical acceptance — ownerTechnical acceptanceSarah A. Al-QarniProject ownerOn behalf of Munirah A. Al-KhalidiApprovedInspected and accepted against the approved acceptance criteria.⁦2025-11-11⁩ 13:34
4Deliverable matched to the contract lineFinancial approvalMazen A. Al-HazmiProcurement & contractsApproved—⁦2025-11-12⁩ 09:00
5Certificate linked to the payment certificateFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2025-11-16⁩ 10:37

Signatures

Evidence against the acceptance criteria

Ghada A. Al-Shahrani

Approved⁦2025-11-09⁩

Inspection & technical acceptance — owner

Sarah A. Al-Qarni

Approved⁦2025-11-11⁩

Deliverable matched to the contract line

Mazen A. Al-Hazmi

Approved⁦2025-11-12⁩

Certificate linked to the payment certificate

Munirah A. Al-Khalidi

Approved⁦2025-11-16⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F08 · version V1

Deliverable completion certificate

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Deliverable acceptance & certificate · version ⁦1⁩

Submitted by Sarah A. Al-Qarni on ⁦2025-11-05⁩

  1. Methodology review

    Evidence against the acceptance criteria

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2025-11-09⁩ at ⁦12:27⁩

  2. Technical acceptance

    Inspection & technical acceptance — owner

    Munirah A. Al-Khalidi · Project owner

    Approved · ⁦2025-11-11⁩ at ⁦13:34⁩ · On behalf of Munirah A. Al-Khalidi (Sarah A. Al-Qarni)

    Inspected and accepted against the approved acceptance criteria.

  3. Financial approval

    Deliverable matched to the contract line

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2025-11-12⁩ at ⁦09:00⁩

  4. Financial approval

    Certificate linked to the payment certificate

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2025-11-16⁩ at ⁦10:37⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2025-11-05⁩

    PRJ-2026-001_2.2_v1.pdf

    Sarah A. Al-Qarni

Only one version so far.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close