SCA ERP System Subtask Last item under this branch 2027-02-27 61% SCA ERP System Planned: 2025-01-12 → 2026-12-31 Forecast: 2025-01-12 → 2027-02-27 Float: 0d
1 Management & governance Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2025-09-26 100% Management & governance Planned: 2025-01-12 → 2025-06-22 Actual: 2025-01-12 → 2025-09-26
1.1 Project plan & baseline Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-06-19 100% Project plan & baseline Planned: 2025-01-12 → 2025-04-21 Actual: 2025-01-12 → 2025-06-19
1.2 Monitoring & reporting Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-09-26 100% Monitoring & reporting Planned: 2025-03-15 → 2025-06-22 Actual: 2025-04-21 → 2025-09-26
Project plan approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-09-26 100% Project plan approved Planned: 2025-06-22 → 2025-06-22 Actual: 2025-09-26 → 2025-09-26 Project plan approved
2 Analysis & design Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-04-12 100% Analysis & design Planned: 2025-05-16 → 2025-10-24 Actual: 2025-07-29 → 2026-04-12
2.1 Business requirements Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-01-03 100% Business requirements Planned: 2025-05-16 → 2025-08-23 Actual: 2025-07-29 → 2026-01-03
2.2 Solution design Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-04-12 100% Solution design Planned: 2025-07-17 → 2025-10-24 Actual: 2025-11-05 → 2026-04-12
Designs approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-04-12 100% Designs approved Planned: 2025-10-24 → 2025-10-24 Actual: 2026-04-12 → 2026-04-12 Designs approved
3 Build Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-11-27 90% Build Planned: 2025-09-17 → 2026-04-27 Forecast: 2026-01-18 → 2026-11-27 Float: 0d
3.1 Release 1 Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-07-20 100% Release 1 Planned: 2025-09-17 → 2025-12-25 Actual: 2026-02-12 → 2026-07-20
3.2 Release 2 Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-10-27 100% Release 2 Planned: 2025-11-17 → 2026-02-25 Actual: 2026-05-22 → 2026-10-27
3.3 Integrations Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-11-27 70% Integrations Planned: 2026-01-18 → 2026-04-27 Forecast: 2026-01-18 → 2026-11-27 Float: 0d Drag to change its duration +214
Build complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-11-27 0% Build complete Planned: 2026-04-27 → 2026-04-27 Forecast: 2026-11-27 → 2026-11-27 Float: 92d Drag to change its dates Build complete
4 Testing & acceptance Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2027-01-12 0% Testing & acceptance Planned: 2026-03-21 → 2026-08-29 Forecast: 2026-11-13 → 2027-01-12 Float: 0d
4.1 System testing Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-12-20 0% System testing Planned: 2026-03-21 → 2026-06-28 Forecast: 2026-11-13 → 2026-12-20 Float: 0d Drag to change its dates +175
4.2 User acceptance testing Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-01-12 0% User acceptance testing Planned: 2026-05-22 → 2026-08-29 Forecast: 2026-12-06 → 2027-01-12 Float: 0d Drag to change its dates +136
Testing & acceptance complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-01-12 0% Testing & acceptance complete Planned: 2026-08-29 → 2026-08-29 Forecast: 2027-01-12 → 2027-01-12 Float: 46d Drag to change its dates Testing & acceptance complete
5 Launch & handover Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2027-02-27 0% Launch & handover Planned: 2026-07-23 → 2026-12-31 Forecast: 2026-12-29 → 2027-02-27 Float: 0d
5.1 Training & change Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-02-04 0% Training & change Planned: 2026-07-23 → 2026-10-30 Forecast: 2026-12-29 → 2027-02-04 Float: 0d Drag to change its dates +97
5.2 Go-live & handover Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-02-27 0% Go-live & handover Planned: 2026-09-23 → 2026-12-31 Forecast: 2027-01-21 → 2027-02-27 Float: 0d Drag to change its dates +58
Final handover Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-02-27 0% Final handover Planned: 2026-12-31 → 2026-12-31 Forecast: 2027-02-27 → 2027-02-27 Float: 0d Drag to change its dates Final handover