Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-005On track4ExecutionWaterfall

SCA Cybersecurity Programme

Add to watchlist

A security operations centre, identity & access management and full ECC compliance.

Budget (BAC)

SAR 38.6M

Actual cost

SAR 33M

⁦85%⁩ of budget

Progress

⁦88%⁩Awaiting acceptance ⁦6%⁩

Estimate at completion

SAR 37.5M

SPI · CPI

1.02Schedule performance index · 1.021.03Cost performance index · 1.03

Forecast finish

⁦2026-12-10⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure22 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 December 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate2 February 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate22 May 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate22 October 2026Closure · Not startedClosure · Not started

Project status card

One page for the periodic update, to print or export and send to the committee and the sponsor.

Issue schedulePeriodic update cards

Shown by your permissionsProject Management Office: 1 project — everything in your scope

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Project status card

28 October 2026 · 17 Jumada I 1448 AH

SCA Cybersecurity Programme

PRJ-2026-005 · Digital Transformation Sector · Operational · WP-2025-005

On track4ExecutionProject manager: Eng. Yasser M. Al-Zahrani · Sponsor: Eng. Majed S. Al-Rasheed
Progress
⁦88%⁩ / ⁦86%⁩
SPI · CPI
1.02 · 1.03
Spend
SAR 33M / SAR 38.6M
Estimate at completion
SAR 37.5M

Schedule

⁦2%⁩ ahead⁦88%⁩

Planned to date ⁦86%⁩

Forecast finish: 2026-12-101 Rajab 1448 AH · On time

SPI1.02Schedule performance index · 1.02CPI1.03Cost performance index · 1.03

Health dimensions

On track

Last update: 2026-10-2716 Jumada I 1448 AH · Up to date

Deliverables

⁦8⁩ of ⁦10⁩ due deliverables accepted on time (⁦80%⁩)

Next milestones

  • Final handover2027-01-0224 Rajab 1448 AH

Top risks

  • Undetected vulnerabilities in legacy systems before SOC onboarding10

Open impediments

  • None

Decisions and changes waiting

  • None

Copilot summary

The scope holds 1 project with a budget of SAR 38.6M: 1 on track and 0 red or critical. Weighted progress is 88% against 86% planned, spend SAR 33M, and EAC SAR 37.5M (SAR 1.1M under).

No project is more than a month behind baseline.

Saudi Contractors Authority · prepared by Eng. Yasser M. Al-Zahrani in MunjazInternal

Status: On track ·Project page

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close