PRJ-2026-005On track4ExecutionWaterfall

SCA Cybersecurity Programme

Add to watchlist

A security operations centre, identity & access management and full ECC compliance.

Budget (BAC)

SAR 38.6M

Actual cost

SAR 33M

⁦85%⁩ of budget

Progress

⁦88%⁩Awaiting acceptance ⁦6%⁩

Estimate at completion

SAR 37.5M

SPI · CPI

1.02Schedule performance index · 1.021.03Cost performance index · 1.03

Forecast finish

⁦2026-12-10⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure22 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 December 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate2 February 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate22 May 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate22 October 2026Closure · Not startedClosure · Not started

Kick-off meeting minutes

Roles, tasks, decisions and the start of execution

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Kick-off meeting minutes

Roles, tasks, decisions and the start of execution

Form no.
SCA-PMO-F06
Template edition
1.2
Version
V1
Form date
⁦2025-02-09⁩
Hijri
10 Shaʻban 1446 AH
ApprovedMTG-KO-005Kick-off — SCA Cybersecurity Programme

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-005
Project
SCA Cybersecurity Programme
Portfolio
Technology & Enterprise Systems Portfolio
Sector
Digital Transformation Sector
Sponsor
Eng. Majed S. Al-Rasheed
Project manager
Eng. Yasser M. Al-Zahrani

1The meetingAuto-filled

MeetingAuto-filled
Kick-off — SCA Cybersecurity Programme
Date and timeAuto-filled
⁦2025-02-09⁩ · 10:00
PlaceAuto-filled
Main meeting room — headquarters
SecretaryAuto-filled
Eng. Yasser M. Al-Zahrani

Purpose

Project kick-off: confirm the roles, the first tasks and the start decisions, and confirm execution starts per the approved charter.

AttendeesTitle
Eng. Majed S. Al-RasheedHead, Digital Transformation Sector
Eng. Nayef H. Al-BuqamiDirector General, Information Technology
Eng. Yasser M. Al-ZahraniDirector, Cybersecurity
Dr. Noura M. Al-OtaibiDirector, Project Management Office
Eng. Hind A. Al-ZahraniMunjaz Platform Administrator

2Roles

PersonRoleDuty
Eng. Majed S. Al-RasheedProject sponsorSponsors the project, decides escalations and material changes
Eng. Nayef H. Al-BuqamiProject ownerApproves the requirements and accepts the deliverables
Eng. Yasser M. Al-ZahraniProject managerRuns the plan, deliverables and risks; files the periodic update card
Dr. Noura M. Al-OtaibiProject Management OfficeFollows the methodology and checks the periodic updates
Eng. Hind A. Al-ZahraniPlatform engineer, cybersecurity programmeDelivers their tasks and uploads the evidence

3Tasks

TaskOwnerDueStatus
Project plan approvedEng. Yasser M. Al-Zahrani⁦2025-07-05⁩Done
Designs approvedEng. Yasser M. Al-Zahrani⁦2025-10-30⁩Done
Build completeEng. Yasser M. Al-Zahrani⁦2026-04-24⁩Done
Testing & acceptance completeEng. Yasser M. Al-Zahrani⁦2026-08-20⁩Done

4Decisions

  1. The charter is the reference for scope, budget and the milestone plan
  2. Change Control Board: Approves scope, cost and schedule changes (Weekly)
  3. PMO Committee: Methodology compliance, data quality, stage gates (Fortnightly)
  4. The periodic update card monthly, before the 5th of the month

5Start of execution

Execution starts on
⁦2025-05-22⁩
Start confirmed
Eng. Majed S. Al-Rasheed · ⁦2025-02-10⁩

Approval logChain: Kick-off minutes approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Yasser M. Al-ZahraniDirector, CybersecuritySubmitted—⁦2025-02-10⁩ 10:49
2Chair’s approval (sponsor)Technical acceptanceEng. Majed S. Al-RasheedProject sponsorApproved—⁦2025-02-11⁩ 12:30
3Minutes against the templateMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2025-02-12⁩ 14:23

Signatures

Minutes against the template

Ghada A. Al-Shahrani

Approved⁦2025-02-12⁩

Chair’s approval (sponsor)

Eng. Majed S. Al-Rasheed

Approved⁦2025-02-11⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F06 · version V1

Kick-off meeting minutes

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Kick-off minutes approval · version ⁦1⁩

Submitted by Eng. Yasser M. Al-Zahrani on ⁦2025-02-10⁩

  1. Methodology review

    Minutes against the template

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2025-02-12⁩ at ⁦14:23⁩

  2. Technical acceptance

    Chair’s approval (sponsor)

    Eng. Majed S. Al-Rasheed · Project sponsor

    Approved · ⁦2025-02-11⁩ at ⁦12:30⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2025-02-09⁩

    The minutes as taken

    Eng. Yasser M. Al-Zahrani

Only one version so far.