PRJ-2026-016At risk4ExecutionWaterfall

Contracting Sector Information Centre & Data Governance

Add to watchlist

Apply NDMO policies, build one master register of contractors, members and projects, and publish sector indicators regularly.

Budget (BAC)

SAR 21.5M

Actual cost

SAR 14M

⁦65%⁩ of budget

Progress

⁦62%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 22.6M

SAR +1.1M

SPI · CPI

0.89Schedule performance index · 0.890.95Cost performance index · 0.95

Forecast finish

⁦2027-01-18⁩

18 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure20 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 June 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 August 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate24 October 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate20 November 2026Closure · Not startedClosure · Not started

Project status card

One page for the periodic update, to print or export and send to the committee and the sponsor.

Issue schedulePeriodic update cards

Shown by your permissionsProject Management Office: 1 project — everything in your scope

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Project status card

28 October 2026 · 17 Jumada I 1448 AH

Contracting Sector Information Centre & Data Governance

PRJ-2026-016 · Regulation & Development Sector · Strategic · WP-2025-016

At risk4ExecutionProject manager: Rahaf I. Al-Nefaie · Sponsor: Eng. Majed S. Al-Rasheed
Progress
⁦62%⁩ / ⁦70%⁩
SPI · CPI
0.89 · 0.95
Spend
SAR 14M / SAR 21.5M
Estimate at completion
SAR 22.6M

Schedule

⁦8%⁩ behind⁦62%⁩

Planned to date ⁦70%⁩

Forecast finish: 2027-01-1810 Shaʻban 1448 AH · 18 days late

SPI0.89Schedule performance index · 0.89CPI0.95Cost performance index · 0.95

Health dimensions

At risk

Last update: 2026-10-2110 Jumada I 1448 AH · Up to date

Deliverables

⁦5⁩ of ⁦9⁩ due deliverables accepted on time (⁦56%⁩)

Next milestones

  • Build complete2026-11-133 Jumada II 1448 AH
  • Testing & acceptance complete2026-12-156 Rajab 1448 AH
  • Final handover2027-01-168 Shaʻban 1448 AH

Top risks

  • Too few accredited data owners in the sectors and departments9

Open impediments

  • None

Decisions and changes waiting

  • None

Copilot summary

The scope holds 1 project with a budget of SAR 21.5M: 0 on track and 0 red or critical. Weighted progress is 62% against 70% planned, spend SAR 14M, and EAC SAR 22.6M (SAR 1.1M over).

No project is more than a month behind baseline.

Saudi Contractors Authority · prepared by Rahaf I. Al-Nefaie in MunjazInternal

Status: At risk ·Project page