PRJ-2026-016At risk4ExecutionWaterfall

Contracting Sector Information Centre & Data Governance

Add to watchlist

Apply NDMO policies, build one master register of contractors, members and projects, and publish sector indicators regularly.

Budget (BAC)

SAR 21.5M

Actual cost

SAR 14M

⁦65%⁩ of budget

Progress

⁦62%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 22.6M

SAR +1.1M

SPI · CPI

0.89Schedule performance index · 0.890.95Cost performance index · 0.95

Forecast finish

⁦2027-01-18⁩

18 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure20 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 June 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 August 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate24 October 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate20 November 2026Closure · Not startedClosure · Not started

Project documents by stage

What each stage requires under the RFP, what has been filed and what is missing, and the evidence tied to deliverables.

Open in the repository
  • ⁦0⁩ of ⁦7⁩ mandatory documents due
  • 7 mandatory documents missing
  • 1 document in the repository

Documents in the project folder

Archived automatically when the project closes, and kept read-only under the retention policy.

Stages and required documents

For each of the five stages, what its gates and forms require: present, missing, or not yet due.

  1. 1Pre-start
    • Project proposal & feasibility studyMandatory· Missing

      Approval gate G1

    • Priority & weight assessmentOptional· Missing

      Annual work plan

  2. 2Initiation
    • Approved project charterMandatory· Missing

      Initiation gate G2

    • Kick-off meeting minutesMandatory· Missing

      Initiation gate G2

  3. 3Planning
    • Project management plan, schedule & baselineMandatory· Missing

      Planning gate G3

    • Contract or purchase orderMandatory· Missing

      Finance & procurement — when there is a contract

    • Technical studies & drawingsOptional· Missing

      Project management plan

  4. 4ExecutionCurrent stage
    • Periodic update cards & status reportsMandatory· Missing

      Periodic update card form

    • Deliverable completion certificatesMandatory· Missing

      Deliverable completion certificate form

    • Corrective plan when off trackOptional· Missing

      Corrective plan form

    • Other documents in the stage

      Sector data governance handbook & master-data policies
  5. 5Closure
    • Project closure & handover formMandatory· Not yet due

      Closure gate G4

    • Lessons learnedMandatory· Not yet due

      Closure gate G4

    • Acceptance test resultsOptional· Not yet due

      Deliverable acceptance

Evidence tied to deliverables

Each deliverable with its repository document and the files that prove it.

  • 016-D1Project plan & baselinePRJ-2026-016_1.1_v1.pdfApprovedDeliverable
  • 016-D2Monitoring & reportingPRJ-2026-016_1.2_v1.pdfApprovedDeliverable
  • 016-D3Business requirementsPRJ-2026-016_2.1_v1.pdfApprovedDeliverable
  • 016-D4Solution designPRJ-2026-016_2.2_v1.pdfApprovedDeliverable
  • 016-D5Release 1PRJ-2026-016_3.1_v1.pdfApprovedDeliverable
  • 016-D6Release 2PRJ-2026-016_3.2_v1.pdfApprovedDeliverable
  • 016-D7IntegrationsPRJ-2026-016_3.3_v1.pdfIn reviewDeliverable
  • 016-D8System testingNo evidence filed yetDraftDeliverable
  • 016-D9User acceptance testingNo evidence filed yetDraftDeliverable
  • 016-D10Training & changeNo evidence filed yetDraftDeliverable
  • 016-D11Go-live & handoverNo evidence filed yetDraftDeliverable