Contracting Sector Information Centre & Data Governance
Add to watchlistApply NDMO policies, build one master register of contractors, members and projects, and publish sector indicators regularly.
Budget (BAC)
Actual cost
65% of budget
Progress
Estimate at completion
SAR +1.1M
SPI · CPI
Forecast finish
18 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure20 November 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate4 June 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate3 August 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate24 October 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate20 November 2026Closure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2025-11-26 | 2026-01-28 | +63 days | Rahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & InnovationP-027r.alnefaie@sca.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2026-02-23 | 2026-06-13 | +110 days | Rahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & InnovationP-027r.alnefaie@sca.sa | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-07-06 | 2026-11-13 | +130 days | Rahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & InnovationP-027r.alnefaie@sca.sa | Late | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-10-03 | 2026-12-15 | +73 days | Rahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & InnovationP-027r.alnefaie@sca.sa | Late | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2026-12-31 | 2027-01-16 | +16 days | Rahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & InnovationP-027r.alnefaie@sca.sa | On track | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
62%Awaiting acceptance
10%Not handed in
28%Deliverable flow
Display options
| Project plan & baseline016-D1 | 5% | CRT-016-01 | Approved | Rahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & InnovationP-027r.alnefaie@sca.sa | Faisal A. Al-Shehri | 2025-10-13 | V1 | 3 of 3 |
| Monitoring & reporting016-D2 | 5% | CRT-016-02 | Approved | Faisal A. Al-ShehriFaisal A. Al-ShehriDirector General, Digital Platforms & Digital Services Portfolio ManagerP-003f.alshehri@sca.sa | Faisal A. Al-Shehri | 2025-11-26 | V1 | 3 of 3 |
| Business requirements016-D3 | 10% | CRT-016-03 | Approved | Faisal A. Al-ShehriFaisal A. Al-ShehriDirector General, Digital Platforms & Digital Services Portfolio ManagerP-003f.alshehri@sca.sa | Faisal A. Al-Shehri | 2026-01-10 | V1 | 3 of 3 |
| Solution design016-D4 | 10% | CRT-016-04 | Approved | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedHead, Digital Transformation SectorP-011m.alrasheed@sca.sa | Faisal A. Al-Shehri | 2026-02-23 | V1 | 3 of 3 |
| Release 1016-D5 | 16% | CRT-016-05 | Approved | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedHead, Digital Transformation SectorP-011m.alrasheed@sca.sa | Faisal A. Al-Shehri | 2026-04-09 | V1 | 3 of 3 |
| Release 2016-D6 | 16% | CRT-016-06 | Approved | Rahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & InnovationP-027r.alnefaie@sca.sa | Faisal A. Al-Shehri | 2026-05-23 | V1 | 3 of 3 |
| Integrations016-D7 | 10% | — | Under review | Faisal A. Al-ShehriFaisal A. Al-ShehriDirector General, Digital Platforms & Digital Services Portfolio ManagerP-003f.alshehri@sca.sa | Faisal A. Al-Shehri | 2026-07-06 | V1 | 1 of 3 |
| System testing016-D8 | 8% | — | Draft | Rahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & InnovationP-027r.alnefaie@sca.sa | Faisal A. Al-Shehri | 2026-08-20 | V0 | 0 of 3 |
| User acceptance testing016-D9 | 8% | — | Draft | Faisal A. Al-ShehriFaisal A. Al-ShehriDirector General, Digital Platforms & Digital Services Portfolio ManagerP-003f.alshehri@sca.sa | Faisal A. Al-Shehri | 2026-10-03 | V0 | 0 of 3 |
| Training & change016-D10 | 6% | — | Draft | Faisal A. Al-ShehriFaisal A. Al-ShehriDirector General, Digital Platforms & Digital Services Portfolio ManagerP-003f.alshehri@sca.sa | Faisal A. Al-Shehri | 2026-11-17 | V0 | 0 of 3 |
| Go-live & handover016-D11 | 6% | — | Draft | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedHead, Digital Transformation SectorP-011m.alrasheed@sca.sa | Faisal A. Al-Shehri | 2026-12-31 | V0 | 0 of 3 |
| Total · 11 | 100% |