Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-016At risk4ExecutionWaterfall

Contracting Sector Information Centre & Data Governance

Add to watchlist

Apply NDMO policies, build one master register of contractors, members and projects, and publish sector indicators regularly.

Budget (BAC)

SAR 21.5M

Actual cost

SAR 14M

⁦65%⁩ of budget

Progress

⁦62%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 22.6M

SAR +1.1M

SPI · CPI

0.89Schedule performance index · 0.890.95Cost performance index · 0.95

Forecast finish

⁦2027-01-18⁩

18 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure20 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 June 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 August 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate24 October 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate20 November 2026Closure · Not startedClosure · Not started

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Form no.
SCA-PMO-F08
Template edition
1.1
Version
V1
Form date
⁦2026-01-28⁩
Hijri
9 Shaʻban 1447 AH
ApprovedCRT-016-02Monitoring & reporting

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-016
Project
Contracting Sector Information Centre & Data Governance
Portfolio
Digital Services & Platforms Portfolio
Sector
Regulation & Development Sector
Sponsor
Eng. Majed S. Al-Rasheed
Project manager
Rahaf I. Al-Nefaie

1The deliverableAuto-filled

DeliverableAuto-filled
Monitoring & reporting
DescriptionAuto-filled
A contractual output tied to its WBS work package.
OwnerAuto-filled
Faisal A. Al-Shehri
VersionAuto-filled
V1
Weight in the projectAuto-filled
⁦5%⁩
DueAuto-filled
⁦2025-11-26⁩

2Evidence of completionAuto-filled

FileVersionByDate
PRJ-2026-016_1.2_v1.pdfV1Faisal A. Al-Shehri⁦2025-10-10⁩

3Inspection and acceptance criteria

CriterionResult
Matches the approved scope of workMet
Quality review with no major findingsMet
Evidence attached and signed by the ownerMet
Met3 of 3
InspectorAuto-filled
Faisal A. Al-Shehri
Accepted byAuto-filled
Eng. Majed S. Al-Rasheed
Acceptance note
Inspected and accepted against the approved acceptance criteria.

4Financial linkAuto-filled

Contract milestoneAuto-filled
Project plan approved
ContractAuto-filled
CTR-2025-017
Payment certificateAuto-filled
Linked when the certificate is raised
Payment against itAuto-filled
—

Approval logChain: Deliverable acceptance & certificate · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Faisal A. Al-ShehriDirector General, Digital Platforms & Digital Services Portfolio ManagerSubmitted—⁦2025-10-10⁩ 12:39
2Evidence against the acceptance criteriaMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2025-10-13⁩ 14:29
3Inspection & technical acceptance — ownerTechnical acceptanceEng. Majed S. Al-RasheedProject ownerOn behalf of Faisal A. Al-ShehriApprovedInspected and accepted against the approved acceptance criteria.⁦2025-10-14⁩ 09:36
4Deliverable matched to the contract lineFinancial approvalMazen A. Al-HazmiProcurement & contractsApproved—⁦2025-10-15⁩ 13:46
5Certificate linked to the payment certificateFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2025-10-19⁩ 14:23

Signatures

Evidence against the acceptance criteria

Ghada A. Al-Shahrani

Approved⁦2025-10-13⁩

Inspection & technical acceptance — owner

Eng. Majed S. Al-Rasheed

Approved⁦2025-10-14⁩

Deliverable matched to the contract line

Mazen A. Al-Hazmi

Approved⁦2025-10-15⁩

Certificate linked to the payment certificate

Munirah A. Al-Khalidi

Approved⁦2025-10-19⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F08 · version V1

Deliverable completion certificate

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Deliverable acceptance & certificate · version ⁦1⁩

Submitted by Faisal A. Al-Shehri on ⁦2025-10-10⁩

  1. Methodology review

    Evidence against the acceptance criteria

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2025-10-13⁩ at ⁦14:29⁩

  2. Technical acceptance

    Inspection & technical acceptance — owner

    Faisal A. Al-Shehri · Project owner

    Approved · ⁦2025-10-14⁩ at ⁦09:36⁩ · On behalf of Faisal A. Al-Shehri (Eng. Majed S. Al-Rasheed)

    Inspected and accepted against the approved acceptance criteria.

  3. Financial approval

    Deliverable matched to the contract line

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2025-10-15⁩ at ⁦13:46⁩

  4. Financial approval

    Certificate linked to the payment certificate

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2025-10-19⁩ at ⁦14:23⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2025-10-10⁩

    PRJ-2026-016_1.2_v1.pdf

    Faisal A. Al-Shehri

Only one version so far.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close