AI insight
No early warning on this project
Only a 41% chance of a further slip on current trends.
Apply NDMO policies, build one master register of contractors, members and projects, and publish sector indicators regularly.
Budget (BAC)
Actual cost
65% of budget
Progress
Estimate at completion
SAR +1.1M
SPI · CPI
Forecast finish
18 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure20 November 2026
A weighted index, not just percent complete; each dimension leads to the tab that explains it.
Health index
80
Solid
Index over the last six reports
May to October 2026
No material change in the health dimensions over the period.
AI insight
Only a 41% chance of a further slip on current trends.
Generated from the live project data
The project is behind plan: 62% done against 70% planned.
SPI 0.89, CPI 0.95.
How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.
The main objective and initiative, the secondary links, and the project’s contribution to its initiative.
Main initiative
SI-2.3.1Sector information & project tracking
The project’s share of the initiative’s project budget (2 projects)
Secondary links
No secondary links
Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.
Counted
62%Awaiting acceptance 10%
Not handed in 28%
6 deliverables accepted
1 deliverable under inspection or acceptance
3 of 5 milestones complete
Earned-value curve
Planned, earned and actual to the data date, cumulative, with the forecast cost tail
Commitments are 76% of budget
0 approvals and 0 open actions on this project
1 open risk, exposure SAR 650K
Impact
0 escalated
6 of 11 approved
4 members