Add to watchlistApply NDMO policies, build one master register of contractors, members and projects, and publish sector indicators regularly.
Budget (BAC)
Actual cost
65% of budget
Progress
Estimate at completion
SAR +1.1M
SPI · CPI
Forecast finish
18 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure20 November 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate4 June 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate3 August 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate24 October 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate20 November 2026Closure · Not startedClosure · Not started
Scope statementRequired at this stage
What the project delivers, what it does not, and when a deliverable counts as accepted.
Apply NDMO policies, build one master register of contractors, members and projects, and publish sector indicators regularly.
In scope
- Apply NDMO policies, build one master register of contractors, members and projects, and publish sector indicators regularly.
- Single sign-on through Nafath
- Integration with internal systems
Out of scope
- Operation and maintenance after the warranty period
- Work outside the approved site or system boundary
Acceptance criteria
- Main deliverable — stage 1Meets the approved specification, signed off by the project owner
- Main deliverable — final stageMeets the approved specification, signed off by the project owner
Scope baselineRequired at this stage
Every approved change creates a new baseline
- 1
SB-1Current2025-08-28
Baseline approved at the planning gate
Budget21.5MFinish2026-12-31
Requirements registerRequired at this stage
6 requirements of five kinds, with the trace status of each
By type
- Business1
- Functional2
- Technical1
- Regulatory1
- Security1
Fully traced
100%
6/6 · linked to a deliverable, task and test
Test passed
17%
1/6 · test result is a pass
Accepted
17%
1/6 · signed off by the business owner
Display options
| REQ-016-01 | An end-to-end digital journey, no walk-in | Business | Must | In progress | Faisal A. Al-ShehriFaisal A. Al-ShehriDirector General, Digital Platforms & Digital Services Portfolio ManagerP-003f.alshehri@sca.sa | SB-1 | |
| REQ-016-02 | Nafath single sign-on | Functional | Must | In progress | Rahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & InnovationP-027r.alnefaie@sca.sa | SB-1 | |
| REQ-016-03 | A user dashboard | Functional | Must | Approved | Faisal A. Al-ShehriFaisal A. Al-ShehriDirector General, Digital Platforms & Digital Services Portfolio ManagerP-003f.alshehri@sca.sa | SB-1 | |
| REQ-016-04 | Integration with internal systems | Technical | Should | In progress | Rahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & InnovationP-027r.alnefaie@sca.sa | SB-1 | |
| REQ-016-05 | WCAG 2.1 accessibility | Regulatory | Should | In progress | Faisal A. Al-ShehriFaisal A. Al-ShehriDirector General, Digital Platforms & Digital Services Portfolio ManagerP-003f.alshehri@sca.sa | SB-1 | |
| REQ-016-06 | Essential cybersecurity controls | Security | Could | In progress | Rahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & InnovationP-027r.alnefaie@sca.sa | SB-1 |
Traceability matrixRequired at this stage
Requirement → deliverable → task → test → acceptance. No requirement has a gap.