PRJ-2026-016At risk4ExecutionWaterfall

Contracting Sector Information Centre & Data Governance

Add to watchlist

Apply NDMO policies, build one master register of contractors, members and projects, and publish sector indicators regularly.

Budget (BAC)

SAR 21.5M

Actual cost

SAR 14M

⁦65%⁩ of budget

Progress

⁦62%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 22.6M

SAR +1.1M

SPI · CPI

0.89Schedule performance index · 0.890.95Cost performance index · 0.95

Forecast finish

⁦2027-01-18⁩

18 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure20 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 June 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 August 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate24 October 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate20 November 2026Closure · Not startedClosure · Not started

Kick-off meeting minutes

Roles, tasks, decisions and the start of execution

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Kick-off meeting minutes

Roles, tasks, decisions and the start of execution

Form no.
SCA-PMO-F06
Template edition
1.2
Version
V1
Form date
⁦2025-08-10⁩
Hijri
16 Safar 1447 AH
ApprovedMTG-KO-016Kick-off — Contracting Sector Information Centre & Data Governance

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-016
Project
Contracting Sector Information Centre & Data Governance
Portfolio
Digital Services & Platforms Portfolio
Sector
Regulation & Development Sector
Sponsor
Eng. Majed S. Al-Rasheed
Project manager
Rahaf I. Al-Nefaie

1The meetingAuto-filled

MeetingAuto-filled
Kick-off — Contracting Sector Information Centre & Data Governance
Date and timeAuto-filled
⁦2025-08-10⁩ · 10:00
PlaceAuto-filled
Main meeting room — headquarters
SecretaryAuto-filled
Rahaf I. Al-Nefaie

Purpose

Project kick-off: confirm the roles, the first tasks and the start decisions, and confirm execution starts per the approved charter.

AttendeesTitle
Eng. Majed S. Al-RasheedHead, Digital Transformation Sector
Faisal A. Al-ShehriDirector General, Digital Platforms & Digital Services Portfolio Manager
Rahaf I. Al-NefaieDirector, Data & Innovation
Dr. Noura M. Al-OtaibiDirector, Project Management Office
Eng. Majed S. Al-RasheedHead, Digital Transformation Sector
Rakan F. Al-MohammadiData Engineer
——

2Roles

PersonRoleDuty
Eng. Majed S. Al-RasheedProject sponsorSponsors the project, decides escalations and material changes
Faisal A. Al-ShehriProject ownerApproves the requirements and accepts the deliverables
Rahaf I. Al-NefaieProject managerRuns the plan, deliverables and risks; files the periodic update card
Dr. Noura M. Al-OtaibiProject Management OfficeFollows the methodology and checks the periodic updates
Eng. Majed S. Al-RasheedProject sponsorDelivers their tasks and uploads the evidence
Rakan F. Al-MohammadiContractor, member & project master-data modelDelivers their tasks and uploads the evidence
—Data governance consultantDelivers their tasks and uploads the evidence

3Tasks

TaskOwnerDueStatus
Project plan approvedRahaf I. Al-Nefaie⁦2025-11-26⁩Done
Designs approvedRahaf I. Al-Nefaie⁦2026-02-23⁩Done
Build completeRahaf I. Al-Nefaie⁦2026-07-06⁩Open
Testing & acceptance completeRahaf I. Al-Nefaie⁦2026-10-03⁩Open

4Decisions

  1. The charter is the reference for scope, budget and the milestone plan
  2. Change Control Board: Approves scope, cost and schedule changes (Weekly)
  3. PMO Committee: Methodology compliance, data quality, stage gates (Fortnightly)
  4. The periodic update card monthly, before the 5th of the month

5Start of execution

Execution starts on
⁦2025-10-24⁩
Start confirmed
Eng. Majed S. Al-Rasheed · ⁦2025-08-11⁩

Approval logChain: Kick-off minutes approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Rahaf I. Al-NefaieDirector, Data & InnovationSubmitted—⁦2025-08-11⁩ 12:33
2Chair’s approval (sponsor)Technical acceptanceEng. Majed S. Al-RasheedProject sponsorApproved—⁦2025-08-12⁩ 12:30
3Minutes against the templateMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2025-08-13⁩ 10:07

Signatures

Minutes against the template

Ghada A. Al-Shahrani

Approved⁦2025-08-13⁩

Chair’s approval (sponsor)

Eng. Majed S. Al-Rasheed

Approved⁦2025-08-12⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F06 · version V1

Kick-off meeting minutes

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Kick-off minutes approval · version ⁦1⁩

Submitted by Rahaf I. Al-Nefaie on ⁦2025-08-11⁩

  1. Methodology review

    Minutes against the template

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2025-08-13⁩ at ⁦10:07⁩

  2. Technical acceptance

    Chair’s approval (sponsor)

    Eng. Majed S. Al-Rasheed · Project sponsor

    Approved · ⁦2025-08-12⁩ at ⁦12:30⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.