PRJ-2026-016At risk4ExecutionWaterfall

Contracting Sector Information Centre & Data Governance

Add to watchlist

Apply NDMO policies, build one master register of contractors, members and projects, and publish sector indicators regularly.

Budget (BAC)

SAR 21.5M

Actual cost

SAR 14M

⁦65%⁩ of budget

Progress

⁦62%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 22.6M

SAR +1.1M

SPI · CPI

0.89Schedule performance index · 0.890.95Cost performance index · 0.95

Forecast finish

⁦2027-01-18⁩

18 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure20 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 June 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 August 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate24 October 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate20 November 2026Closure · Not startedClosure · Not started

Schedule & Gantt

The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.

Finish-date drift

⁦+16⁩ days vs approved

Baseline (original = approved)⁦2026-12-31⁩
Current forecast⁦2027-01-16⁩
By earned schedule⁦2027-09-24⁩
Critical activities
6
of ⁦8⁩ open activities
Late activities
5
past their baseline finish
Schedule performance
0.64
earned ÷ planned value
Next milestone
in 16 days
Build complete
Expand allCollapse all
Activity
Contracting Sector Information Centre & Data GovernancePlanned: ⁦2025-08-03⁩ → ⁦2026-12-31⁩Forecast: ⁦2025-08-03⁩ → ⁦2027-01-16⁩Float: ⁦0⁩d
Management & governancePlanned: ⁦2025-08-03⁩ → ⁦2025-11-26⁩Actual: ⁦2025-08-03⁩ → ⁦2026-01-28⁩
Project plan & baselinePlanned: ⁦2025-08-03⁩ → ⁦2025-10-13⁩Actual: ⁦2025-08-03⁩ → ⁦2025-11-20⁩
Monitoring & reportingPlanned: ⁦2025-09-16⁩ → ⁦2025-11-26⁩Actual: ⁦2025-10-10⁩ → ⁦2026-01-28⁩
Project plan approvedPlanned: ⁦2025-11-26⁩ → ⁦2025-11-26⁩Actual: ⁦2026-01-28⁩ → ⁦2026-01-28⁩Project plan approved
Analysis & designPlanned: ⁦2025-10-31⁩ → ⁦2026-02-23⁩Actual: ⁦2025-12-18⁩ → ⁦2026-06-13⁩
Business requirementsPlanned: ⁦2025-10-31⁩ → ⁦2026-01-10⁩Actual: ⁦2025-12-18⁩ → ⁦2026-04-06⁩
Solution designPlanned: ⁦2025-12-14⁩ → ⁦2026-02-23⁩Actual: ⁦2026-02-24⁩ → ⁦2026-06-13⁩
Designs approvedPlanned: ⁦2026-02-23⁩ → ⁦2026-02-23⁩Actual: ⁦2026-06-13⁩ → ⁦2026-06-13⁩Designs approved
BuildPlanned: ⁦2026-01-28⁩ → ⁦2026-07-06⁩Forecast: ⁦2026-04-26⁩ → ⁦2026-11-13⁩Float: ⁦0⁩d
Release 1Planned: ⁦2026-01-28⁩ → ⁦2026-04-09⁩Actual: ⁦2026-05-03⁩ → ⁦2026-08-21⁩
Release 2Planned: ⁦2026-03-13⁩ → ⁦2026-05-23⁩Actual: ⁦2026-07-11⁩ → ⁦2026-10-26⁩
IntegrationsPlanned: ⁦2026-04-26⁩ → ⁦2026-07-06⁩Forecast: ⁦2026-04-26⁩ → ⁦2026-11-13⁩Float: ⁦0⁩dDrag to change its duration+130
Build completePlanned: ⁦2026-07-06⁩ → ⁦2026-07-06⁩Forecast: ⁦2026-11-13⁩ → ⁦2026-11-13⁩Float: ⁦64⁩dDrag to change its datesBuild complete
Testing & acceptancePlanned: ⁦2026-06-10⁩ → ⁦2026-10-03⁩Forecast: ⁦2026-11-03⁩ → ⁦2026-12-15⁩Float: ⁦0⁩d
System testingPlanned: ⁦2026-06-10⁩ → ⁦2026-08-20⁩Forecast: ⁦2026-11-03⁩ → ⁦2026-11-29⁩Float: ⁦0⁩dDrag to change its dates+101
User acceptance testingPlanned: ⁦2026-07-24⁩ → ⁦2026-10-03⁩Forecast: ⁦2026-11-19⁩ → ⁦2026-12-15⁩Float: ⁦0⁩dDrag to change its dates+73
Testing & acceptance completePlanned: ⁦2026-10-03⁩ → ⁦2026-10-03⁩Forecast: ⁦2026-12-15⁩ → ⁦2026-12-15⁩Float: ⁦32⁩dDrag to change its datesTesting & acceptance complete
Launch & handoverPlanned: ⁦2026-09-07⁩ → ⁦2026-12-31⁩Forecast: ⁦2026-12-05⁩ → ⁦2027-01-16⁩Float: ⁦0⁩d
Training & changePlanned: ⁦2026-09-07⁩ → ⁦2026-11-17⁩Forecast: ⁦2026-12-05⁩ → ⁦2026-12-31⁩Float: ⁦0⁩dDrag to change its dates+44
Go-live & handoverPlanned: ⁦2026-10-21⁩ → ⁦2026-12-31⁩Forecast: ⁦2026-12-21⁩ → ⁦2027-01-16⁩Float: ⁦0⁩dDrag to change its dates+16
Final handoverPlanned: ⁦2026-12-31⁩ → ⁦2026-12-31⁩Forecast: ⁦2027-01-16⁩ → ⁦2027-01-16⁩Float: ⁦0⁩dDrag to change its datesFinal handover
  • Activities (forecast)
  • Baseline
  • Slip past baseline
  • Critical
  • Milestone
  • Phase / element
  • Today

⁦22⁩ rows shown · Data date ⁦2026-10-28⁩

AI schedule analysis

Computed from the current plan: ⁦8⁩ open activities, data date ⁦2026-10-28⁩

Critical-path risk⁦95%⁩ confidence

The critical path runs through ⁦5⁩ activities with no float

Every day lost on this chain is a day lost at launch. No other activity has three weeks of float or less.
Unrealistic durations⁦78%⁩ confidence

“Integrations” needs a pace ⁦3.5⁩× faster than it has kept

It earned ⁦77%⁩ in 185 days; the forecast assumes the rest in 16 days. At the pace so far it finishes on ⁦2026-12-22⁩.

Slippage pattern⁦84%⁩ confidence

Milestones slip 78 days on average

Each milestone’s slip in days, in date order; the later ones slip more than the early ones.

63
110
130
73
16
G1G2G3G4G5

The critical chain

In date order, to final acceptance