Project Tracking Platform — National Phase
Add to watchlistA platform where owners, contractors and the ministry follow the progress, milestones and delays of registered construction projects in every region.
Budget (BAC)
Actual cost
1% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
InitiationStage 2 of 5
Next gate:Planning6 September 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate8 July 2026Initiation · Current stageInitiation · Current stage
- Gate into «Planning»DecisionNot held yetDate6 September 2026Planning · Not startedPlanning · Not started
- Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2026-12-23 | 2027-01-24 | +32 days | Rahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & InnovationP-027r.alnefaie@sca.sa | At risk | 0 | Not requested |
| Designs approvedMS-G2 | Project | 2027-03-16 | 2027-04-10 | +25 days | Rahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & InnovationP-027r.alnefaie@sca.sa | At risk | 0 | Not requested |
| Build completeMS-G3 | Contractual | 2027-07-18 | 2027-08-02 | +15 days | Rahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & InnovationP-027r.alnefaie@sca.sa | On track | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2027-10-09 | 2027-10-17 | +8 days | Rahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & InnovationP-027r.alnefaie@sca.sa | On track | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2027-12-31 | 2028-01-01 | +1 days | Rahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & InnovationP-027r.alnefaie@sca.sa | On track | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
1%Awaiting acceptance
0%Not handed in
99%Deliverable flow
Display options
| Project plan & baseline023-D1 | 1% | CRT-023-01 | Approved | Rahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & InnovationP-027r.alnefaie@sca.sa | Faisal A. Al-Shehri | 2026-11-11 | V1 | 3 of 3 |
| Monitoring & reporting023-D2 | 4% | — | Draft | Faisal A. Al-ShehriFaisal A. Al-ShehriDirector General, Digital Platforms & Digital Services Portfolio ManagerP-003f.alshehri@sca.sa | Faisal A. Al-Shehri | 2026-12-23 | V0 | 0 of 3 |
| Business requirements023-D3 | 9% | — | Draft | Faisal A. Al-ShehriFaisal A. Al-ShehriDirector General, Digital Platforms & Digital Services Portfolio ManagerP-003f.alshehri@sca.sa | Faisal A. Al-Shehri | 2027-02-02 | V0 | 0 of 3 |
| Solution design023-D4 | 9% | — | Draft | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedHead, Digital Transformation SectorP-011m.alrasheed@sca.sa | Faisal A. Al-Shehri | 2027-03-16 | V0 | 0 of 3 |
| Release 1023-D5 | 14% | — | Draft | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedHead, Digital Transformation SectorP-011m.alrasheed@sca.sa | Faisal A. Al-Shehri | 2027-04-26 | V0 | 0 of 3 |
| Release 2023-D6 | 14% | — | Draft | Rahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & InnovationP-027r.alnefaie@sca.sa | Faisal A. Al-Shehri | 2027-06-07 | V0 | 0 of 3 |
| Integrations023-D7 | 14% | — | Draft | Faisal A. Al-ShehriFaisal A. Al-ShehriDirector General, Digital Platforms & Digital Services Portfolio ManagerP-003f.alshehri@sca.sa | Faisal A. Al-Shehri | 2027-07-18 | V0 | 0 of 3 |
| System testing023-D8 | 10% | — | Draft | Rahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & InnovationP-027r.alnefaie@sca.sa | Faisal A. Al-Shehri | 2027-08-29 | V0 | 0 of 3 |
| User acceptance testing023-D9 | 10% | — | Draft | Faisal A. Al-ShehriFaisal A. Al-ShehriDirector General, Digital Platforms & Digital Services Portfolio ManagerP-003f.alshehri@sca.sa | Faisal A. Al-Shehri | 2027-10-09 | V0 | 0 of 3 |
| Training & change023-D10 | 8% | — | Draft | Faisal A. Al-ShehriFaisal A. Al-ShehriDirector General, Digital Platforms & Digital Services Portfolio ManagerP-003f.alshehri@sca.sa | Faisal A. Al-Shehri | 2027-11-20 | V0 | 0 of 3 |
| Go-live & handover023-D11 | 7% | — | Draft | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedHead, Digital Transformation SectorP-011m.alrasheed@sca.sa | Faisal A. Al-Shehri | 2027-12-31 | V0 | 0 of 3 |
| Total · 11 | 100% |