Project Tracking Platform — National Phase Subtask Last item under this branch 2028-01-01 1% Project Tracking Platform — National Phase Planned: 2026-09-06 → 2027-12-31 Forecast: 2026-09-06 → 2028-01-01 Float: 0d
1 Management & governance Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2027-01-24 13% Management & governance Planned: 2026-09-06 → 2026-12-23 Forecast: 2026-09-06 → 2027-01-24 Float: 0d
1.1 Project plan & baseline Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-12-17 25% Project plan & baseline Planned: 2026-09-06 → 2026-11-11 Forecast: 2026-09-06 → 2026-12-17 Float: 0d Drag to change its duration +36
1.2 Monitoring & reporting Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-01-24 0% Monitoring & reporting Planned: 2026-10-17 → 2026-12-23 Forecast: 2026-11-24 → 2027-01-24 Float: 0d Drag to change its dates +32
Project plan approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-01-24 0% Project plan approved Planned: 2026-12-23 → 2026-12-23 Forecast: 2027-01-24 → 2027-01-24 Float: 342d Drag to change its dates Project plan approved
2 Analysis & design Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2027-04-10 0% Analysis & design Planned: 2026-11-28 → 2027-03-16 Forecast: 2027-01-01 → 2027-04-10 Float: 0d
2.1 Business requirements Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-03-03 0% Business requirements Planned: 2026-11-28 → 2027-02-02 Forecast: 2027-01-01 → 2027-03-03 Float: 0d Drag to change its dates +29
2.2 Solution design Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-04-10 0% Solution design Planned: 2027-01-08 → 2027-03-16 Forecast: 2027-02-08 → 2027-04-10 Float: 0d Drag to change its dates +25
Designs approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-04-10 0% Designs approved Planned: 2027-03-16 → 2027-03-16 Forecast: 2027-04-10 → 2027-04-10 Float: 266d Drag to change its dates Designs approved
3 Build Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2027-08-02 0% Build Planned: 2027-02-19 → 2027-07-18 Forecast: 2027-03-18 → 2027-08-02 Float: 0d
3.1 Release 1 Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-05-18 0% Release 1 Planned: 2027-02-19 → 2027-04-26 Forecast: 2027-03-18 → 2027-05-18 Float: 0d Drag to change its dates +22
3.2 Release 2 Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-06-25 0% Release 2 Planned: 2027-04-01 → 2027-06-07 Forecast: 2027-04-25 → 2027-06-25 Float: 0d Drag to change its dates +18
3.3 Integrations Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-08-02 0% Integrations Planned: 2027-05-13 → 2027-07-18 Forecast: 2027-06-02 → 2027-08-02 Float: 0d Drag to change its dates +15
Build complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-08-02 0% Build complete Planned: 2027-07-18 → 2027-07-18 Forecast: 2027-08-02 → 2027-08-02 Float: 152d Drag to change its dates Build complete
4 Testing & acceptance Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2027-10-17 0% Testing & acceptance Planned: 2027-06-23 → 2027-10-09 Forecast: 2027-07-10 → 2027-10-17 Float: 0d
4.1 System testing Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-09-09 0% System testing Planned: 2027-06-23 → 2027-08-29 Forecast: 2027-07-10 → 2027-09-09 Float: 0d Drag to change its dates +11
4.2 User acceptance testing Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-10-17 0% User acceptance testing Planned: 2027-08-04 → 2027-10-09 Forecast: 2027-08-17 → 2027-10-17 Float: 0d Drag to change its dates +8
Testing & acceptance complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-10-17 0% Testing & acceptance complete Planned: 2027-10-09 → 2027-10-09 Forecast: 2027-10-17 → 2027-10-17 Float: 76d Drag to change its dates Testing & acceptance complete
5 Launch & handover Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2028-01-01 0% Launch & handover Planned: 2027-09-14 → 2027-12-31 Forecast: 2027-09-24 → 2028-01-01 Float: 0d
5.1 Training & change Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-11-24 0% Training & change Planned: 2027-09-14 → 2027-11-20 Forecast: 2027-09-24 → 2027-11-24 Float: 0d Drag to change its dates +4
5.2 Go-live & handover Task after this Starts when this one finishes Milestone after this Falls on its finish 2028-01-01 0% Go-live & handover Planned: 2027-10-26 → 2027-12-31 Forecast: 2027-11-01 → 2028-01-01 Float: 0d Drag to change its dates +1
Final handover Task after this Starts when this one finishes Milestone after this Falls on its finish 2028-01-01 0% Final handover Planned: 2027-12-31 → 2027-12-31 Forecast: 2028-01-01 → 2028-01-01 Float: 0d Drag to change its dates Final handover