PRJ-2026-028On track4ExecutionWaterfall

SCA Strategy Refresh & Execution Plans

Add to watchlist

Turning the four axes and 34 initiatives of the SCA strategy into portfolios, initiatives and KPIs aligned with Saudi Vision 2030.

Budget (BAC)

SAR 3.2M

Actual cost

SAR 2.2M

⁦70%⁩ of budget

Progress

⁦70%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 3.2M

SPI · CPI

1.03Schedule performance index · 1.031.00Cost performance index · 1.00

Forecast finish

⁦2026-12-15⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure27 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 March 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 May 2026Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate8 June 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate27 November 2026Closure · Not startedClosure · Not started

Kick-off meeting minutes

Roles, tasks, decisions and the start of execution

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Kick-off meeting minutes

Roles, tasks, decisions and the start of execution

Form no.
SCA-PMO-F06
Template edition
1.2
Version
V1
Form date
⁦2026-05-10⁩
Hijri
23 Dhuʻl-Qiʻdah 1447 AH
In approvalMTG-KO-028Kick-off — SCA Strategy Refresh & Execution Plans

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-028
Project
SCA Strategy Refresh & Execution Plans
Portfolio
Institutional Excellence & Governance Portfolio
Sector
Strategy & Institutional Excellence Sector
Sponsor
Dr. Mohammed I. Al-Subaie
Project manager
Abeer H. Al-Shamrani

1The meetingAuto-filled

MeetingAuto-filled
Kick-off — SCA Strategy Refresh & Execution Plans
Date and timeAuto-filled
⁦2026-05-10⁩ · 10:00
PlaceAuto-filled
Main meeting room — headquarters
SecretaryAuto-filled
Abeer H. Al-Shamrani

Purpose

Project kick-off: confirm the roles, the first tasks and the start decisions, and confirm execution starts per the approved charter.

AttendeesTitle
Dr. Mohammed I. Al-SubaieHead, Strategy & Institutional Excellence Sector
Dr. Amal F. Al-SudairiDirector General, Strategy & Performance
Abeer H. Al-ShamraniHead of Strategy Management
Dr. Noura M. Al-OtaibiDirector, Project Management Office
Dr. Mohammed I. Al-SubaieHead, Strategy & Institutional Excellence Sector
Dr. Noura M. Al-OtaibiDirector, Project Management Office

2Roles

PersonRoleDuty
Dr. Mohammed I. Al-SubaieProject sponsorSponsors the project, decides escalations and material changes
Dr. Amal F. Al-SudairiProject ownerApproves the requirements and accepts the deliverables
Abeer H. Al-ShamraniProject managerRuns the plan, deliverables and risks; files the periodic update card
Dr. Noura M. Al-OtaibiProject Management OfficeFollows the methodology and checks the periodic updates
Dr. Mohammed I. Al-SubaieProject sponsorDelivers their tasks and uploads the evidence
Dr. Noura M. Al-OtaibiGovernance adviser to the strategy refreshDelivers their tasks and uploads the evidence

3Tasks

TaskOwnerDueStatus
Project plan approvedAbeer H. Al-Shamrani⁦2026-06-27⁩Done
Designs approvedAbeer H. Al-Shamrani⁦2026-08-09⁩Done
Build completeAbeer H. Al-Shamrani⁦2026-09-21⁩Done
Testing & acceptance completeAbeer H. Al-Shamrani⁦2026-11-02⁩Open

4Decisions

  1. The charter is the reference for scope, budget and the milestone plan
  2. Change Control Board: Approves scope, cost and schedule changes (Weekly)
  3. PMO Committee: Methodology compliance, data quality, stage gates (Fortnightly)
  4. The periodic update card monthly, before the 5th of the month

5Start of execution

Execution starts on
⁦2026-06-08⁩
Start confirmed
Awaiting confirmation after the meeting

Approval logChain: Kick-off minutes approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Abeer H. Al-ShamraniHead of Strategy ManagementSubmitted—⁦2026-10-26⁩ 09:24
2Minutes against the templateMethodology reviewApproval enginePMO — analystPre-breach alert—⁦2026-10-28⁩ 08:00

Signatures

Minutes against the template

Ghada A. Al-Shahrani

Awaiting decision

Chair’s approval (sponsor)

Dr. Mohammed I. Al-Subaie

Later

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F06 · version V1

Kick-off meeting minutes

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Kick-off minutes approval · version ⁦1⁩

Submitted by Abeer H. Al-Shamrani on ⁦2026-10-26⁩

  1. Methodology review

    Minutes against the template

    Ghada A. Al-Shahrani · PMO — analyst

    Delegated to Dr. Noura M. Al-Otaibi

    Due todayAction time limit about to lapse · Limit 2 working daysLimit 2 working days · Due ⁦2026-10-28⁩

    Pre-breach alert at ⁦75%⁩ — sent ⁦2026-10-28⁩

  2. Technical acceptance

    Chair’s approval (sponsor)

    Dr. Mohammed I. Al-Subaie · Project sponsor

    Delegated to Dr. Noura M. Al-Otaibi

    Limit 2 working days · Expected by ⁦2026-11-01⁩

Previous versions

Every version is kept with its status and what changed.