Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-028On track4ExecutionWaterfall

SCA Strategy Refresh & Execution Plans

Add to watchlist

Turning the four axes and 34 initiatives of the SCA strategy into portfolios, initiatives and KPIs aligned with Saudi Vision 2030.

Budget (BAC)

SAR 3.2M

Actual cost

SAR 2.2M

⁦70%⁩ of budget

Progress

⁦70%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 3.2M

SPI · CPI

1.03Schedule performance index · 1.031.00Cost performance index · 1.00

Forecast finish

⁦2026-12-15⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure27 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 March 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 May 2026Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate8 June 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate27 November 2026Closure · Not startedClosure · Not started

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to work3.1M⁦15⁩ elements
Unallocated contingency96KSAR 160K
Budget at completion3.2MPRJ-2026-028
Weighted progress⁦70%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSAR MActualSAR MLinksDeliverables
Project226⁦2026-05-03⁩⁦2026-12-15⁩⁦70%⁩3.102.24—
1
Phase70⁦2026-05-03⁩⁦2026-07-12⁩⁦100%⁩0.310.32—
1.1
WBS element43⁦2026-05-03⁩⁦2026-06-15⁩⁦100%⁩0.160.160 / 1
1.2
WBS element43⁦2026-05-30⁩⁦2026-07-12⁩⁦100%⁩0.160.161 / 2
2
Phase70⁦2026-06-26⁩⁦2026-09-04⁩⁦100%⁩0.620.64—
2.1
WBS element43⁦2026-06-26⁩⁦2026-08-08⁩⁦100%⁩0.310.321 / 1
2.2
WBS element43⁦2026-07-23⁩⁦2026-09-04⁩⁦100%⁩0.310.321 / 2
3
Phase68⁦2026-08-19⁩⁦2026-10-26⁩⁦100%⁩0.930.96—
3.1
WBS element43⁦2026-08-19⁩⁦2026-10-01⁩⁦100%⁩0.470.481 / 1
3.2
WBS element41⁦2026-09-15⁩⁦2026-10-26⁩⁦100%⁩0.470.481 / 2
4
Phase75⁦2026-09-08⁩⁦2026-11-22⁩⁦34%⁩0.930.32—
4.1
WBS element64⁦2026-09-08⁩⁦2026-11-11⁩⁦67%⁩0.470.321 / 1
4.2
WBS element18⁦2026-11-04⁩⁦2026-11-22⁩⁦0%⁩0.47—1 / 2
5
Phase30⁦2026-11-15⁩⁦2026-12-15⁩⁦0%⁩0.31——
5.1
WBS element18⁦2026-11-15⁩⁦2026-12-03⁩⁦0%⁩0.16—1 / 1
5.2
WBS element18⁦2026-11-26⁩⁦2026-12-14⁩⁦0%⁩0.16—1 / 1
Total⁦70%⁩3.102.24
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close