PRJ-2026-033On hold3PlanningConstruction

Wadi Al-Dawasir Vocational Qualification Centre

Add to watchlist

A permanent training and skills-test centre for the south of the Riyadh region, waiting for the land handover and title deed.

Budget (BAC)

SAR 210M

Actual cost

SAR 4.2M

⁦2%⁩ of budget

Progress

⁦2%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 210M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-12-31⁩

184 days behind baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution15 July 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate31 December 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 March 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate15 July 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Suspension, resumption & cancellation

The decision, the rationale and the approvals

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Suspension, resumption & cancellation

The decision, the rationale and the approvals

Form no.
SCA-PMO-F10
Template edition
1.0
Version
V1
Form date
⁦2026-10-21⁩
Hijri
10 Jumada I 1448 AH
In approvalSTS-033-2Resumption — Wadi Al-Dawasir Vocational Qualification Centre

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-033
Project
Wadi Al-Dawasir Vocational Qualification Centre
Portfolio
Academy & Qualification Centres Portfolio
Sector
Qualification & Training Sector
Sponsor
Eng. Turki A. Al-Anazi
Project manager
Eng. Shahad M. Al-Malki

1The decision asked for

Action
Resumption
Status nowAuto-filled
Suspended
Status afterAuto-filled
Active
Requested onAuto-filled
⁦2026-10-21⁩

2Rationale

The title deed is issued and the land handed over; we ask to resume and tender the design works in December.

3Effect on the projectAuto-filled

Approved budget

SAR 210M

Committed

SAR 4.6M

Actual

SAR 4.2M

Progress

⁦2%⁩

A suspended project keeps its stage and resumes in it; its progress is frozen in the portfolio’s progress while suspended.

Approval logChain: Suspension, resumption & cancellation · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Shahad M. Al-MalkiDirector, Academy FacilitiesSubmitted—⁦2026-10-21⁩ 10:01
2PMO opinionMethodology reviewApproval enginePMO — directorPre-breach alert—⁦2026-10-25⁩ 08:00

Signatures

PMO opinion

Dr. Noura M. Al-Otaibi

Awaiting decision

Effect on financial commitments

Munirah A. Al-Khalidi

Later

Sponsor’s decision

Eng. Turki A. Al-Anazi

Later

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F10 · version V1

Suspension, resumption & cancellation

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Suspension, resumption & cancellation · version ⁦1⁩

Submitted by Eng. Shahad M. Al-Malki on ⁦2026-10-21⁩

  1. Methodology review

    PMO opinion

    Dr. Noura M. Al-Otaibi · PMO — director
    3 working days overdueAction time limit exceeded · Limit 2 working daysLimit 2 working days · Due ⁦2026-10-25⁩

    Pre-breach alert at ⁦75%⁩ — sent ⁦2026-10-25⁩

  2. Financial approval

    Effect on financial commitments

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Delegated to Khalid N. Al-Mutairi

    Limit 2 working days · Expected by ⁦2026-10-27⁩

  3. Technical acceptance

    Sponsor’s decision

    Eng. Turki A. Al-Anazi · Project sponsor

    Limit 3 working days · Expected by ⁦2026-11-01⁩

Steps that do not apply to this record

  • Contracts suspended or resumed — the condition «Contract link?» does not hold
  • Project Approval Committee — the condition «Suspension longer than the sponsor’s authority?» does not holdFrom the authority matrix
  • Secretary-General — the condition «Cancelling a project of SAR 100M or more?» does not holdFrom the authority matrix

Previous versions

Every version is kept with its status and what changed.

  1. V1In approvalCurrent⁦2026-10-21⁩

    The title deed is issued and the land handed over; we ask to resume and tender the design works in December.

    Eng. Shahad M. Al-Malki

Only one version so far.