Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-033On hold3PlanningConstruction

Wadi Al-Dawasir Vocational Qualification Centre

Add to watchlist

A permanent training and skills-test centre for the south of the Riyadh region, waiting for the land handover and title deed.

Budget (BAC)

SAR 210M

Actual cost

SAR 4.2M

⁦2%⁩ of budget

Progress

⁦2%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 210M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-12-31⁩

184 days behind baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution15 July 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate31 December 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 March 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate15 July 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to work203.7M⁦17⁩ elements
Unallocated contingency6.3MSAR 10.5M
Budget at completion210MPRJ-2026-033
Weighted progress⁦2%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSAR MActualSAR MLinksDeliverables
Project1,041⁦2026-03-01⁩⁦2029-01-05⁩⁦2%⁩203.704.20—
1
Phase351⁦2026-03-01⁩⁦2027-02-15⁩⁦34%⁩12.224.20—
1.1
WBS element277⁦2026-03-01⁩⁦2026-12-03⁩⁦67%⁩6.114.200 / 1
1.2
WBS element110⁦2026-10-28⁩⁦2027-02-15⁩⁦0%⁩6.11—1 / 2
2
Phase179⁦2027-01-05⁩⁦2027-07-03⁩⁦0%⁩24.44——
2.1
WBS element110⁦2027-01-05⁩⁦2027-04-25⁩⁦0%⁩12.22—1 / 1
2.2
WBS element110⁦2027-03-15⁩⁦2027-07-03⁩⁦0%⁩12.22—1 / 2
3
Phase248⁦2027-05-23⁩⁦2028-01-26⁩⁦0%⁩77.41——
3.1
WBS element110⁦2027-05-23⁩⁦2027-09-10⁩⁦0%⁩25.80—1 / 1
3.2
WBS element110⁦2027-07-31⁩⁦2027-11-18⁩⁦0%⁩25.80—1 / 1
3.3
WBS element110⁦2027-10-08⁩⁦2028-01-26⁩⁦0%⁩25.80—1 / 2
4
Phase248⁦2027-12-16⁩⁦2028-08-20⁩⁦0%⁩61.11——
4.1
WBS element110⁦2027-12-16⁩⁦2028-04-04⁩⁦0%⁩20.37—1 / 1
4.2
WBS element110⁦2028-02-23⁩⁦2028-06-12⁩⁦0%⁩20.37—1 / 1
4.3
WBS element110⁦2028-05-02⁩⁦2028-08-20⁩⁦0%⁩20.37—1 / 2
5
Phase179⁦2028-07-10⁩⁦2029-01-05⁩⁦0%⁩28.52——
5.1
WBS element110⁦2028-07-10⁩⁦2028-10-28⁩⁦0%⁩14.26—1 / 1
5.2
WBS element110⁦2028-09-17⁩⁦2029-01-05⁩⁦0%⁩14.26—1 / 1
Total⁦2%⁩203.704.20
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close