SO-2.1 · Build capability and innovation in the sector

Sector capability & the Academy

At riskIncludes non-project workA Cornerstone of Sector Development

The Irtiqaa portal for contractors’ self-assessment and capability plans, and the SCA Academy’s learning platform and professional tracks.

⁦43%⁩

Initiative weighted progress

⁦43.3%⁩

Projects’ contribution × progress, plus the other work’s share × its progress

Linked projects’ progress

⁦39.4%⁩

Σ contribution × progress, projects only

Contributions assigned

⁦100%⁩

Complete and approved

Primary projects’ budget

13.9M

2 primary projects

Linked projects and their contributions

Strategy management approves each share; every change is kept in the initiative’s history

ProjectLinkContributionActual progressContribution × progress
Irtiqaa Portal — Release 2

PRJ-2026-027

Primary⁦45%⁩⁦63%⁩⁦28.4%⁩
SCA Academy — Learning Platform & Professional Tracks

PRJ-2026-029

Primary⁦30%⁩⁦4%⁩⁦1.2%⁩

Non-project work

The accredited qualification programmes the Academy runs in person for contractors and sector workers

Other work⁦25%⁩⁦55%⁩⁦13.8%⁩

Linked projects’ progress

Σ (contribution × progress) = ⁦29.6%⁩ points ÷ shares counted ⁦75%⁩ = ⁦39.4%⁩

Initiative progress

(⁦29.6%⁩ points from projects + ⁦13.8%⁩ from other work) ÷ ⁦100%⁩ = ⁦43.3%⁩

Impact KPIs & benefits

Measured apart from delivery progress: an initiative can be well advanced with no impact yet, and the other way round

Impact KPIs

The strategic KPIs the initiative moves

Benefits

Benefits registered for its projects, planned vs realised

No benefits registered for these projects yet; they are recorded at closure and handover.

These KPIs and benefits do not enter the weighted progress above, and progress does not enter them.

Three separate measures

An example from this initiative: Irtiqaa Portal — Release 2

1Deliverable weight in the project

⁦40.0%⁩

Weight of «Build» among its deliverables

Deliverable weights add up to 100% inside the project; it progresses as they are accepted.

See where it comes from

2Project weight in the portfolio

⁦20.5%⁩

Its relative weight in Institutional Excellence & Governance Portfolio

Set by the project weight model; it feeds portfolio progress: relative weight × actual progress.

See where it comes from

3Contribution to the initiative

⁦45%⁩

Its contribution to «Sector capability & the Academy»

Approved by strategy management; it feeds this initiative’s progress only.

Each is set in its own place and moves neither of the others: changing a deliverable’s weight touches neither the project’s portfolio weight nor its contribution.