PRJ-2026-027At risk4ExecutionHybrid

Irtiqaa Portal — Release 2

Add to watchlist

A portal to grow contractors’ capability: a self-assessment, a development plan and qualification programmes matched to the gaps.

Budget (BAC)

SAR 6.4M

Actual cost

SAR 4.1M

⁦64%⁩ of budget

Progress

⁦63%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 6.5M

SAR +131K

SPI · CPI

0.88Schedule performance index · 0.880.98Cost performance index · 0.98

Forecast finish

⁦2027-01-31⁩

31 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure27 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 September 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate2 November 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate9 January 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate27 November 2026Closure · Not startedClosure · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

−9

May to October 2026

No material change in the health dimensions over the period.

Copilot summary

Generated from the live project data

The project is behind plan: ⁦63%⁩ done against ⁦72%⁩ planned.

SPI ⁦0.88⁩, CPI ⁦0.98⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: A Leading, Sustainable OrganisationSO-4.4Leadership and human capital

Main initiative

SI-2.1.1Sector capability & the Academy

Contribution to the initiative⁦46%⁩

The project’s share of the initiative’s project budget (2 projects)

Secondary links

No secondary links

Annual work-plan line
WP-2025-027
Classification
Strategic

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦63%⁩

Awaiting acceptance ⁦10%⁩

Not handed in ⁦27%⁩

6 deliverables accepted

  • Release 1⁦16%⁩
  • Release 2⁦16%⁩
  • Business requirements⁦11%⁩
  • Solution design⁦10%⁩
  • Project plan & baseline⁦5%⁩
  • Monitoring & reporting⁦5%⁩

1 deliverable under inspection or acceptance

  • Integrations⁦10%⁩

Progress & earned value

⁦3⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦86%⁩ of budget

4.1M/ 6.4M131Kprojected overrun(⁦2.0%⁩)
Actual spend
4.1M
Committed
5.5M
Approved budget
6.4M
Estimate at completion
6.5M

Next milestones

  • Provisional acceptance⁦2026-12-20⁩was ⁦2026-11-27⁩Late
  • Closure⁦2027-01-31⁩was ⁦2026-12-31⁩Late

Waiting on someone

⁦0⁩ approvals and ⁦0⁩ open actions on this project

Approvals & requests

From «My actions» for this project

  • No approvals pending

Actions

⁦0⁩ open

  • No actions on this project

Change requests

Cost and schedule impact

  • No change requests

Risks & impediments

1 open risk, exposure SAR 250K

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩Probability: Likely · Impact: MajorHigh · Score ⁦16⁩Probability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩1Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩RSK-0040Low uptake of the Irtiqaa self-assessment among small contractorsProbability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical0
  • High0
  • Medium1
  • Low0

Open impediments

⁦0⁩ escalated

  • No open impediments

Deliverables

⁦6⁩ of ⁦11⁩ approved

  • Project plan & baseline027-D1 · V1 · CRT-027-01⁦5%⁩Ghada A. Al-Shahrani⁦2025-12-30⁩2025-12-3010 Rajab 1447 AHApproved
  • Monitoring & reporting027-D2 · V1 · CRT-027-02⁦5%⁩Abdulmajeed R. Al-Dosari⁦2026-02-05⁩2026-02-0517 Shaʻban 1447 AHApproved
  • Business requirements027-D3 · V1 · CRT-027-03⁦11%⁩Abdulmajeed R. Al-Dosari⁦2026-03-14⁩2026-03-1425 Ramadan 1447 AHApproved
  • Solution design027-D4 · V1 · CRT-027-04⁦10%⁩Sarah A. Al-Qarni⁦2026-04-19⁩2026-04-192 Dhuʻl-Qiʻdah 1447 AHApproved
  • Release 1027-D5 · V1 · CRT-027-05⁦16%⁩Sarah A. Al-Qarni⁦2026-05-26⁩2026-05-269 Dhuʻl-Hijjah 1447 AHApproved
  • Release 2027-D6 · V1 · CRT-027-06⁦16%⁩Ghada A. Al-Shahrani⁦2026-07-01⁩2026-07-0116 Muharram 1448 AHApproved
  • Integrations027-D7 · V1⁦10%⁩Abdulmajeed R. Al-Dosari82 days overdue2026-08-0724 Safar 1448 AHIn review
  • System testing027-D8 · V0⁦8%⁩Ghada A. Al-Shahrani46 days overdue2026-09-121 Rabiʻ II 1448 AHDraft
  • User acceptance testing027-D9 · V0⁦7%⁩Abdulmajeed R. Al-Dosari9 days overdue2026-10-198 Jumada I 1448 AHDraft
  • Training & change027-D10 · V0⁦6%⁩Abdulmajeed R. Al-DosariIn 27 days2026-11-2414 Jumada II 1448 AHDraft
  • Go-live & handover027-D11 · V0⁦6%⁩Sarah A. Al-QarniIn 64 days2026-12-3122 Rajab 1448 AHDraft

Team, contracts & documents

Team

4 members

Ghada A. Al-Shahrani · Director, Qualification Programmes & CapabilitySarah A. Al-Qarni · Head, Corporate Support SectorLama S. Al-Harbi · Senior Business Analyst — Contractor ServicesNouf M. Al-Balawi · Change Management Specialist
  • Ghada A. Al-ShahraniGhada A. Al-ShahraniDirector, Qualification Programmes & CapabilityProject managerP-029g.alshahrani@sca.sa⁦50%⁩
  • Sarah A. Al-QarniSarah A. Al-QarniHead, Corporate Support SectorProject sponsorP-012s.alqarni@sca.sa⁦10%⁩
  • Lama S. Al-HarbiLama S. Al-HarbiSenior Business Analyst — Contractor ServicesChange impact on the Irtiqaa assessment proceduresP-006l.alharbi@sca.sa⁦15%⁩
  • Nouf M. Al-BalawiNouf M. Al-BalawiChange Management SpecialistInternal communications planP-035n.albalawi@sca.sa⁦45%⁩

Documents

  • No documents yet

Meetings

  • No meetings scheduled