PRJ-2026-027At risk4ExecutionHybrid
Irtiqaa Portal — Release 2
Add to watchlistA portal to grow contractors’ capability: a self-assessment, a development plan and qualification programmes matched to the gaps.
Project managerGhada A. Al-ShahraniProject sponsorSarah A. Al-QarniProgrammeInstitutional Excellence & Capability Programme
Budget (BAC)
SAR 6.4M
Actual cost
SAR 4.1M
64% of budget
Progress
63%Awaiting acceptance 10%
Estimate at completion
SAR 6.5M
SAR +131K
SPI · CPI
0.88Schedule performance index · 0.880.98Cost performance index · 0.98
Forecast finish
2027-01-31
31 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure27 November 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate3 September 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate2 November 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate9 January 2026Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate27 November 2026Closure · Not startedClosure · Not started