Irtiqaa Portal — Release 2
Add to watchlistA portal to grow contractors’ capability: a self-assessment, a development plan and qualification programmes matched to the gaps.
Budget (BAC)
Actual cost
64% of budget
Progress
Estimate at completion
SAR +131K
SPI · CPI
Forecast finish
31 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure27 November 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate3 September 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate2 November 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate9 January 2026Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate27 November 2026Closure · Not startedClosure · Not started
Closure readiness
Closure planned after the forecast finish on 2027-01-31
A preview of what closure will need, with the planned dates, and the lessons captured so far.
Closure checklist
Seven mandatory items before any project closes.
- 1
Deliverables acceptedNot started
Final acceptance of every deliverable
Abdulmajeed R. Al-DosariPlanned 2027-01-21
- 2
Financial closureNot started
Spend reconciled, commitments closed
Khalid N. Al-MutairiPlanned 2027-02-20
- 3
Contract closureNot started
Contracts closed, retention released
Khalid N. Al-MutairiPlanned 2027-03-02
- 4
Documents archivedNot started
Documents archived with classification
Ghada A. Al-ShahraniPlanned 2027-02-25
- 5
Lessons learnedNot started
Lessons-learned session
Ghada A. Al-ShahraniPlanned 2027-02-15
- 6
Benefits owner assignedNot started
Benefits handed to their owner with a measurement plan
Abdulmajeed R. Al-DosariPlanned 2027-02-10
- 7
Final report approvedNot started
Final report and its approval
Ghada A. Al-ShahraniPlanned 2027-03-07
Post-implementation review
Did it reach its goal? Did it stay on budget? Were the benefits realised? What did we learn and improve?
The review comes after closure
About three months after the forecast finish (2027-01-31), with the sponsor and the benefits owner.
Lessons learned
0 lessons — offered automatically to similar projects when they are created.
No lessons captured yet
Capture what the team learned during delivery; closure needs at least one.
Benefits handover
Each benefit moves from the project manager to an owner who measures it after closure.
No benefits recorded for this project.