PRJ-2026-027At risk4ExecutionHybrid

Irtiqaa Portal — Release 2

Add to watchlist

A portal to grow contractors’ capability: a self-assessment, a development plan and qualification programmes matched to the gaps.

Budget (BAC)

SAR 6.4M

Actual cost

SAR 4.1M

⁦64%⁩ of budget

Progress

⁦63%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 6.5M

SAR +131K

SPI · CPI

0.88Schedule performance index · 0.880.98Cost performance index · 0.98

Forecast finish

⁦2027-01-31⁩

31 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure27 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 September 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate2 November 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate9 January 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate27 November 2026Closure · Not startedClosure · Not started

Baselines

The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.

  1. Original

    Original baseline

    v1.0Approved & lockedVersion A
    Finish
    ⁦2026-12-31⁩
    Budget
    SAR 6.4M
    ⁦16⁩ activities

    Approved with the project plan at the planning gate.

    Approved ⁦2025-11-02⁩ · by Sarah A. Al-Qarni

  2. Working

    Working baseline

    v2.0-draftWorking draftVersion B
    Finish
    ⁦2027-01-30⁩
    ⁦+30⁩ days
    Budget
    SAR 6.4M
    ⁦16⁩ activities

    Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.

    Created ⁦2026-10-28⁩ · by Ghada A. Al-Shahrani

    Edit in the schedule

Compare two versions

What changed from version A to version B

Finish

⁦2026-12-31⁩⁦2027-01-30⁩

⁦+30⁩ days

Budget

SAR 6.4MSAR 6.4M

⁦0.00⁩ SAR M

Milestones moved

5 / 5

Milestones: A to B

Each line starts at the milestone’s date in A and ends at its date in B

2026-072027-01
  • Project plan approved⁦+47⁩
  • Designs approved⁦+83⁩
  • Build complete⁦+96⁩
  • Testing & acceptance complete⁦+63⁩
  • Final handover⁦+30⁩

Version AVersion B

Cost by WBS element

Difference in SAR millions from A to B

  • 1Management & governance⁦+0.03⁩
  • 2Analysis & design⁦+0.05⁩
  • 3Build⁦+0.13⁩
  • 4Testing & acceptance⁦+0.08⁩
  • 5Launch & handover⁦+0.06⁩

Version history

Every saved version with its reason and reference

  1. Working baselinev2.0-draftWorking draftFollows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.⁦2026-10-28⁩by Ghada A. Al-Shahrani
  2. Original baselinev1.0Approved & lockedApproved with the project plan at the planning gate.⁦2025-11-02⁩by Sarah A. Al-Qarni