Irtiqaa Portal — Release 2
Add to watchlistA portal to grow contractors’ capability: a self-assessment, a development plan and qualification programmes matched to the gaps.
Budget (BAC)
Actual cost
64% of budget
Progress
Estimate at completion
SAR +131K
SPI · CPI
Forecast finish
31 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure27 November 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate3 September 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate2 November 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate9 January 2026Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate27 November 2026Closure · Not startedClosure · Not started