PRJ-2026-007 · From item 2
SCA Academy Campus, RiyadhPlanned to date 82%
- SPI
- 0.70
- Forecast finish
- 2027-06-01
- Budget
- SAR 640M
152 days lateMaterial risks: 3Open impediments: 4Corrective plan CP-2026-03
Change requests with complete files, week 43.
Held on
21 October 202613:00 – 14:10
60 of 60 min
Approve the previous minutes
ApprovalEng. Ibrahim A. Al-Ghamdi
5 min
Academy campus — 150-day extension
DecisionEng. Shahad M. Al-Malki
30 min
Qassim centre — axes 12–16 foundation redesign
DecisionEng. Ahmed Y. Asiri
25 min
1. Approve the previous minutes
Meeting 40 minutes approved.
2. Academy campus — 150-day extension
CR-2026-006Deferred pending the independent engineer; Finance abstained.
3. Qassim centre — axes 12–16 foundation redesign
CR-2026-010At SAR 8.4M on a revised baseline it exceeds the change committee’s authority; sent up to the Projects Steering Committee.
Voting rule: Simple majority; a Finance objection on impact above SAR 5M sends it to the Projects Steering Committee
Academy campus extension deferred pending the independent engineer’s report
DEC-2026-040Hold
For 4Against 0Abstain 1Carried
They show in the task register and on the owner’s calendar
No tasks from this meeting yet
Quorum: Four of six members, including Finance
At least 4 voting members needed
2 files
Drafted by the assistant from the agenda, the minutes, the decisions and the tasks. Review it before approval.
Shown only to invitees and the PMO, and leaves out what your permissions do not let you see.
Built automatically from the projects on the agenda: a card per project, the decisions needed, the support requested and the overdue tasks.
PRJ-2026-007 · From item 2
SCA Academy Campus, RiyadhPlanned to date 82%
152 days lateMaterial risks: 3Open impediments: 4Corrective plan CP-2026-03
PRJ-2026-020 · From item 3
Qassim Vocational Qualification CentrePlanned to date 55%
64 days lateMaterial risks: 1Open impediments: 1Corrective plan CP-2026-04
Agenda item needing a decision · CR-2026-006
Academy campus — 150-day extensionFrom item 2
Agenda item needing a decision · CR-2026-010
Qassim centre — axes 12–16 foundation redesignFrom item 3
Change request awaiting decision · CR-2026-005
Variation 7: revise the central HVAC systemSCA Academy Campus, Riyadh
Corrective plan awaiting approval · CP-2026-03
SCA Academy Campus, RiyadhISS-0109 · SCA Academy Campus, Riyadh
A decision· Asked from: Executive Committee
A decision to accept an equivalent façade alternative on the consultant’s advice, or to extend the supply period
CP-2026-03 · SCA Academy Campus, Riyadh
A decision· Asked from: Executive Committee
A decision to accept an equivalent façade on the consultant’s advice
ACT-0311 · Eng. Ibrahim A. Al-Ghamdi