Execution
Change request
The change, its impact analysis and the approval decision
- Form no.
- SCA-PMO-F09
- Template edition
- 3.1
- Version
- V1
- Form date
- 2026-10-09
- Hijri
- 28 Rabiʻ II 1448 AH
Auto-filled — Filled by the platform from the project record, not typed.
- Project code
- PRJ-2026-001
- Project
- SCA ERP System
- Portfolio
- Technology & Enterprise Systems Portfolio
- Sector
- Digital Transformation Sector
- Sponsor
- Sarah A. Al-Qarni
- Project manager
- Dana S. Al-Saleh
1The change
- TitleAuto-filled
- Increase the customisation & integration budget
- KindAuto-filled
- Budget
- Requested byAuto-filled
- Dana S. Al-Saleh
- Raised onAuto-filled
- 2026-10-09
Reason
Customisations and Etimad integration missed in the tender book
Justification
Without them the financial module cannot go live and the manual Etimad link remains
2Impact analysis
Cost
SAR +6.8M
Schedule
+45 days
Risk
16 → 9
Benefits
+3%
Risk impact
Covers the contingency overrun
Benefits impact
Month-end close in 5 days instead of 12
3The approval decision
The PMO’s recommendation
The PMO recommends approval after the independent estimate review
- Change Committee decision
- Not taken yet
- Decided on
- —
- Decision number
- —
Conditions
- The independent estimate review before signature
Approval logChain: Change request approval · version 5
Every decision on the form — who, their role, the note and the time. It prints with the form.
| # | Step | Kind | Name | Decision | Note | Date & time |
|---|---|---|---|---|---|---|
| 1 | Author | — | Dana S. Al-SalehDirector, Enterprise Systems & Integration | Submitted | — | 2026-10-09 11:08 |
| 2 | Project manager | Technical acceptance | Dana S. Al-SalehProject manager | Approved | — | 2026-10-11 13:52 |
| 3 | PMO review & impact analysis | Methodology review | Ghada A. Al-ShahraniPMO — analyst | Approved | — | 2026-10-13 14:59 |
| 4 | Financial impact | Financial approval | Approval engineFinance | Pre-breach alert | — | 2026-10-15 08:00 |
Signatures
Project manager
Dana S. Al-Saleh
Approved2026-10-11
PMO review & impact analysis
Ghada A. Al-Shahrani
Approved2026-10-13
Financial impact
Munirah A. Al-Khalidi
Awaiting decision
Change Committee
Dr. Mohammed I. Al-Subaie
Later