PRJ-2026-001Off track4ExecutionHybrid

SCA ERP System

Remove from watchlist

One integrated system for the Authority’s finance, procurement and HR, connected to the Etimad platform.

Early warning: ⁦86%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SAR 64.5M

Actual cost

SAR 44.7M

⁦69%⁩ of budget

Progress

⁦61%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 73.3M

SAR +8.8M

SPI · CPI

0.82Schedule performance index · 0.820.88Cost performance index · 0.88

Forecast finish

⁦2027-02-27⁩

58 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure4 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate13 November 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate12 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate7 May 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate4 November 2026Closure · Not startedClosure · Not started

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Form no.
SCA-PMO-F01
Template edition
2.1
Version
V2
Form date
⁦2024-06-16⁩
Hijri
10 Dhuʻl-Hijjah 1445 AH
ApprovedDMD-2026-001SCA ERP System

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-001
Project
SCA ERP System
Portfolio
Technology & Enterprise Systems Portfolio
Sector
Digital Transformation Sector
Sponsor
Sarah A. Al-Qarni
Project manager
Dana S. Al-Saleh

1The proposalAuto-filled

TitleAuto-filled
SCA ERP System
Proposed byAuto-filled
Dana S. Al-Saleh
DepartmentAuto-filled
Enterprise Systems & Integration Department
Submitted onAuto-filled
⁦2024-06-16⁩
Proposal numberAuto-filled
DMD-2026-001

2Justification

One integrated system for the Authority’s finance, procurement and HR, connected to the Etimad platform.

3Objectives

  1. A sustainable financial base
  2. A mature operating model and accountability

Strategic objectives served

  • SO-4.3 — A sustainable financial base
  • SO-4.2 — A mature operating model and accountability

4Expected benefits

KindBenefit
No benefits recorded yet

5Cost & feasibility

Estimated cost

SAR 64.5M

Funding

The owning sector’s approved budget

Cost lineAmount
Main contractSAR 46.4M
Supervision & consultingSAR 9.1M
Internal teamSAR 5.8M
Contingency reserve (5%)SAR 3.2M
TotalSAR 64.5M

6Initial risks

RiskLevelProposed response
Customisation and Etimad integration costs exceeding the approved contingencyHighTreated in the risk management plan
Late migration and reconciliation of historical financial dataMediumTreated in the risk management plan
Implementation consultants’ contracts ending before go-liveMediumTreated in the risk management plan

Approval logChain: Proposal & feasibility approval · version ⁦4⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Dana S. Al-SalehDirector, Enterprise Systems & IntegrationSubmitted—⁦2024-06-16⁩ 09:24
2Line manager endorsementTechnical acceptanceEng. Reem K. Al-DosariThe requester’s line managerApproved—⁦2024-06-17⁩ 13:04
3PMO reviewMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2024-06-20⁩ 14:11
4Portfolio manager reviewTechnical acceptanceEng. Nayef H. Al-BuqamiPortfolio managerApprovedConsistent with the portfolio plan and its priorities.⁦2024-06-23⁩ 09:18
5Cost & funding reviewFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2024-06-24⁩ 09:00
6Project Approval CommitteeTechnical acceptanceDr. Noura M. Al-OtaibiProject Approval CommitteeApproved—⁦2024-06-26⁩ 11:32

Signatures

Line manager endorsement

Eng. Reem K. Al-Dosari

Approved⁦2024-06-17⁩

PMO review

Ghada A. Al-Shahrani

Approved⁦2024-06-20⁩

Portfolio manager review

Eng. Nayef H. Al-Buqami

Approved⁦2024-06-23⁩

Cost & funding review

Munirah A. Al-Khalidi

Approved⁦2024-06-24⁩

Project Approval Committee

Dr. Noura M. Al-Otaibi

Approved⁦2024-06-26⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F01 · version V2

Project proposal & feasibility study

Prints the form and its approval log on A4.

Project charter

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Proposal & feasibility approval · version ⁦4⁩

Submitted by Dana S. Al-Saleh on ⁦2024-06-16⁩

  1. Technical acceptance

    Line manager endorsement

    Eng. Reem K. Al-Dosari · The requester’s line manager

    Approved · ⁦2024-06-17⁩ at ⁦13:04⁩

  2. Methodology review

    PMO review

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2024-06-20⁩ at ⁦14:11⁩

  3. Technical acceptance

    Portfolio manager review

    Eng. Nayef H. Al-Buqami · Portfolio manager

    Approved · ⁦2024-06-23⁩ at ⁦09:18⁩

    Consistent with the portfolio plan and its priorities.

  4. Financial approval

    Cost & funding review

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2024-06-24⁩ at ⁦09:00⁩

  5. Technical acceptance

    Project Approval Committee

    Dr. Noura M. Al-Otaibi · Project Approval Committee

    Approved · ⁦2024-06-26⁩ at ⁦11:32⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2024-07-07⁩

    Approved after the PMO’s comments

    • Cost estimate updated after indicative quotes
    • Initial risks and their responses added

    Dana S. Al-Saleh

  2. V1Returned for edit⁦2024-06-16⁩

    First draft — returned to complete the cost and risks