PRJ-2026-009At risk4ExecutionHybrid

SCA Systems Migration to the Cloud

Add to watchlist

Move 46 systems and applications to a licensed in-Kingdom cloud under the data classification framework and cloud controls.

Budget (BAC)

SAR 52M

Actual cost

SAR 25.2M

⁦48%⁩ of budget

Progress

⁦47%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SAR 53.6M

SAR +1.6M

SPI · CPI

0.89Schedule performance index · 0.890.97Cost performance index · 0.97

Forecast finish

⁦2027-03-21⁩

21 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure8 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate2 April 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate1 June 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate11 September 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate8 January 2027Closure · Not startedClosure · Not started

Project status card

One page for the periodic update, to print or export and send to the committee and the sponsor.

Issue schedulePeriodic update cards

Shown by your permissionsProject Management Office: 1 project — everything in your scope

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Project status card

28 October 2026 · 17 Jumada I 1448 AH

SCA Systems Migration to the Cloud

PRJ-2026-009 · Digital Transformation Sector · Operational · WP-2025-009

At risk4ExecutionProject manager: Eng. Omar H. Bawazir · Sponsor: Eng. Majed S. Al-Rasheed
Progress
⁦47%⁩ / ⁦53%⁩
SPI · CPI
0.89 · 0.97
Spend
SAR 25.2M / SAR 52M
Estimate at completion
SAR 53.6M

Schedule

⁦6%⁩ behind⁦47%⁩

Planned to date ⁦53%⁩

Forecast finish: 2027-03-2113 Shawwal 1448 AH · 21 days late

SPI0.89Schedule performance index · 0.89CPI0.97Cost performance index · 0.97

Health dimensions

At risk

Last update: 2026-10-2413 Jumada I 1448 AH · Up to date

Deliverables

⁦5⁩ of ⁦8⁩ due deliverables accepted on time (⁦63%⁩)

Next milestones

  • Build complete2026-12-2011 Rajab 1448 AH
  • Testing & acceptance complete2027-02-0225 Shaʻban 1448 AH
  • Final handover2027-03-1810 Shawwal 1448 AH

Top risks

  • Cloud consumption costs above estimate9

Open impediments

  • None

Decisions and changes waiting

  • None

Copilot summary

The scope holds 1 project with a budget of SAR 52M: 0 on track and 0 red or critical. Weighted progress is 47% against 53% planned, spend SAR 25.2M, and EAC SAR 53.6M (SAR 1.6M over).

No project is more than a month behind baseline.

Saudi Contractors Authority · prepared by Eng. Omar H. Bawazir in MunjazInternal

Status: At risk ·Project page