PRJ-2026-009At risk4ExecutionHybrid

SCA Systems Migration to the Cloud

Add to watchlist

Move 46 systems and applications to a licensed in-Kingdom cloud under the data classification framework and cloud controls.

Budget (BAC)

SAR 52M

Actual cost

SAR 25.2M

⁦48%⁩ of budget

Progress

⁦47%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SAR 53.6M

SAR +1.6M

SPI · CPI

0.89Schedule performance index · 0.890.97Cost performance index · 0.97

Forecast finish

⁦2027-03-21⁩

21 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure8 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate2 April 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate1 June 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate11 September 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate8 January 2027Closure · Not startedClosure · Not started

Project charter

Objective, scope, deliverables, roles and budget

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Initiation

Project charter

Objective, scope, deliverables, roles and budget

Form no.
SCA-PMO-F04
Template edition
3.0
Version
V2
Form date
⁦2025-05-30⁩
Hijri
3 Dhuʻl-Hijjah 1446 AH
ApprovedPRJ-2026-009SCA Systems Migration to the Cloud

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-009
Project
SCA Systems Migration to the Cloud
Portfolio
Technology & Enterprise Systems Portfolio
Sector
Digital Transformation Sector
Sponsor
Eng. Majed S. Al-Rasheed
Project manager
Eng. Omar H. Bawazir

1Objective

Background

Move 46 systems and applications to a licensed in-Kingdom cloud under the data classification framework and cloud controls.

Project objectives

  1. Strong technical capabilities

2Scope

In scope

  • Move 46 systems and applications to a licensed in-Kingdom cloud under the data classification framework and cloud controls.
  • Migration from legacy systems
  • ERP integration

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

3Deliverables and milestones

DeliverableDue
Project management plan⁦2025-06-27⁩
Main deliverable — stage 1⁦2026-04-22⁩
Main deliverable — final stage⁦2026-12-01⁩
Final report⁦2027-02-28⁩
MilestoneDate
Charter approved⁦2025-05-30⁩
Contract signed⁦2025-09-11⁩
50% of works complete⁦2026-04-22⁩
Provisional acceptance⁦2027-01-08⁩
Closure⁦2027-02-28⁩

4RolesAuto-filled

SponsorAuto-filled
Eng. Majed S. Al-Rasheed
Project ownerAuto-filled
Eng. Nayef H. Al-Buqami
Project managerAuto-filled
Eng. Omar H. Bawazir
StakeholderRole
Project sponsorDecisions and funding
Project ownerAccepts deliverables, owns benefits
Project Management Office (PMO)Governance and compliance
Governance bodyRoleCadence
Change Control BoardApproves scope, cost and schedule changesWeekly
PMO CommitteeMethodology compliance, data quality, stage gatesFortnightly
Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly

5BudgetAuto-filled

LineAmount
Main contractSAR 37.4M
Supervision & consultingSAR 7.3M
Internal teamSAR 4.7M
Contingency reserve (5%)SAR 2.6M
Approved budgetSAR 52M

Funding

The owning sector’s approved budget

6Success criteria and constraints

Success criteria

  • Delivered within the approved budget
  • On the approved date ±5%
  • Target benefits within 12 months

Constraints

  • Stay within the approved budget
  • Comply with the Government Tenders & Procurement Law

Assumptions

  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

Approval logChain: Project charter approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Omar H. BawazirDirector, IT InfrastructureSubmitted—⁦2025-05-21⁩ 10:00
2PMO complianceMethodology reviewDr. Noura M. Al-OtaibiPMO — directorApproved—⁦2025-05-24⁩ 12:30
3Project ownerTechnical acceptanceEng. Nayef H. Al-BuqamiProject ownerApproved—⁦2025-05-27⁩ 09:45
4Budget funding confirmedFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2025-05-28⁩ 11:10
5Sponsor approvalTechnical acceptanceEng. Majed S. Al-RasheedProject sponsorApproved—⁦2025-05-30⁩ 11:00

Signatures

PMO compliance

Dr. Noura M. Al-Otaibi

Approved⁦2025-05-24⁩

Project owner

Eng. Nayef H. Al-Buqami

Approved⁦2025-05-27⁩

Budget funding confirmed

Munirah A. Al-Khalidi

Approved⁦2025-05-28⁩

Sponsor approval

Eng. Majed S. Al-Rasheed

Approved⁦2025-05-30⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F04 · version V2

Project charter

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project charter approval · version ⁦1⁩

Submitted by Eng. Omar H. Bawazir on ⁦2025-05-21⁩

  1. Methodology review

    PMO compliance

    Dr. Noura M. Al-Otaibi · PMO — director

    Approved · ⁦2025-05-24⁩ at ⁦12:30⁩

  2. Technical acceptance

    Project owner

    Eng. Nayef H. Al-Buqami · Project owner

    Approved · ⁦2025-05-27⁩ at ⁦09:45⁩

  3. Financial approval

    Budget funding confirmed

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2025-05-28⁩ at ⁦11:10⁩

  4. Technical acceptance

    Sponsor approval

    Eng. Majed S. Al-Rasheed · Project sponsor

    Approved · ⁦2025-05-30⁩ at ⁦11:00⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2025-05-30⁩

    Approved version

    • PMO comments addressed

    Eng. Omar H. Bawazir

  2. V1Returned for edit⁦2025-05-11⁩

    First draft

    • Returned to detail the budget

    Eng. Omar H. Bawazir