SCA Systems Migration to the Cloud
Add to watchlistMove 46 systems and applications to a licensed in-Kingdom cloud under the data classification framework and cloud controls.
Budget (BAC)
Actual cost
48% of budget
Progress
Estimate at completion
SAR +1.6M
SPI · CPI
Forecast finish
21 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure8 January 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate2 April 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate1 June 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate11 September 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate8 January 2027Closure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2025-10-22 | 2026-01-25 | +95 days | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@sca.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2026-02-09 | 2026-07-28 | +169 days | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@sca.sa | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-07-23 | 2026-12-20 | +150 days | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@sca.sa | Late | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-11-10 | 2027-02-02 | +84 days | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@sca.sa | At risk | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2027-02-28 | 2027-03-18 | +18 days | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@sca.sa | On track | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
47%Awaiting acceptance
12%Not handed in
41%Deliverable flow
Display options
| Project plan & baseline009-D1 | 5% | CRT-009-01 | Approved | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@sca.sa | Eng. Nayef H. Al-Buqami | 2025-08-28 | V1 | 3 of 3 |
| Monitoring & reporting009-D2 | 5% | CRT-009-02 | Approved | Eng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDirector General, Information TechnologyP-017n.albuqami@sca.sa | Eng. Nayef H. Al-Buqami | 2025-10-22 | V1 | 3 of 3 |
| Business requirements009-D3 | 11% | CRT-009-03 | Approved | Eng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDirector General, Information TechnologyP-017n.albuqami@sca.sa | Eng. Nayef H. Al-Buqami | 2025-12-16 | V1 | 3 of 3 |
| Solution design009-D4 | 10% | CRT-009-04 | Approved | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedHead, Digital Transformation SectorP-011m.alrasheed@sca.sa | Eng. Nayef H. Al-Buqami | 2026-02-09 | V1 | 3 of 3 |
| Release 1009-D5 | 16% | CRT-009-05 | Approved | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedHead, Digital Transformation SectorP-011m.alrasheed@sca.sa | Eng. Nayef H. Al-Buqami | 2026-04-05 | V1 | 3 of 3 |
| Release 2009-D6 | 12% | — | Under review | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@sca.sa | Eng. Nayef H. Al-Buqami | 2026-05-29 | V1 | 1 of 3 |
| Integrations009-D7 | 11% | — | Draft | Eng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDirector General, Information TechnologyP-017n.albuqami@sca.sa | Eng. Nayef H. Al-Buqami | 2026-07-23 | V0 | 0 of 3 |
| System testing009-D8 | 9% | — | Draft | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@sca.sa | Eng. Nayef H. Al-Buqami | 2026-09-16 | V0 | 0 of 3 |
| User acceptance testing009-D9 | 9% | — | Draft | Eng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDirector General, Information TechnologyP-017n.albuqami@sca.sa | Eng. Nayef H. Al-Buqami | 2026-11-10 | V0 | 0 of 3 |
| Training & change009-D10 | 6% | — | Draft | Eng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDirector General, Information TechnologyP-017n.albuqami@sca.sa | Eng. Nayef H. Al-Buqami | 2027-01-04 | V0 | 0 of 3 |
| Go-live & handover009-D11 | 6% | — | Draft | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedHead, Digital Transformation SectorP-011m.alrasheed@sca.sa | Eng. Nayef H. Al-Buqami | 2027-02-28 | V0 | 0 of 3 |
| Total · 11 | 100% |