Project status card
28 October 2026 · 17 Jumada I 1448 AH
Solar Power for SCA Buildings & Centres
PRJ-2026-010 · Corporate Support Sector · Operational · WP-2025-010
- Progress
- 58% / 57%
- SPI · CPI
- 1.02 · 1.01
- Spend
- SAR 55.1M / SAR 96M
- Estimate at completion
- SAR 95.1M
Schedule
Planned to date 57%
Forecast finish: 2027-04-2215 Dhuʻl-Qiʻdah 1448 AH · On time
SPI1.02Schedule performance index · 1.02CPI1.01Cost performance index · 1.01Health dimensions
Last update: 2026-10-2615 Jumada I 1448 AH · Up to date
Deliverables
7 of 9 due deliverables accepted on time (78%)
Next milestones
- Testing & acceptance complete2027-03-0526 Ramadan 1448 AH
- Final handover2027-04-3023 Dhuʻl-Qiʻdah 1448 AH
Top risks
- None
Open impediments
- None
Decisions and changes waiting
- None
Copilot summary
The scope holds 1 project with a budget of SAR 96M: 1 on track and 0 red or critical. Weighted progress is 58% against 57% planned, spend SAR 55.1M, and EAC SAR 95.1M (SAR 1M under).
No project is more than a month behind baseline.