PRJ-2026-010On track4ExecutionConstruction

Solar Power for SCA Buildings & Centres

Add to watchlist

6 MW of rooftop and carport solar across 14 SCA buildings and centres, the largest a ground array at the Tabuk site.

Budget (BAC)

SAR 96M

Actual cost

SAR 55.1M

⁦57%⁩ of budget

Progress

⁦58%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 95.1M

SPI · CPI

1.02Schedule performance index · 1.021.01Cost performance index · 1.01

Forecast finish

⁦2027-04-22⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure26 February 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate1 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate2 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate6 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate26 February 2027Closure · Not startedClosure · Not started

Project status card

One page for the periodic update, to print or export and send to the committee and the sponsor.

Issue schedulePeriodic update cards

Shown by your permissionsProject Management Office: 1 project — everything in your scope

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Project status card

28 October 2026 · 17 Jumada I 1448 AH

Solar Power for SCA Buildings & Centres

PRJ-2026-010 · Corporate Support Sector · Operational · WP-2025-010

On track4ExecutionProject manager: Eng. Mishari K. Al-Otaibi · Sponsor: Eng. Turki A. Al-Anazi
Progress
⁦58%⁩ / ⁦57%⁩
SPI · CPI
1.02 · 1.01
Spend
SAR 55.1M / SAR 96M
Estimate at completion
SAR 95.1M

Schedule

⁦1%⁩ ahead⁦58%⁩

Planned to date ⁦57%⁩

Forecast finish: 2027-04-2215 Dhuʻl-Qiʻdah 1448 AH · On time

SPI1.02Schedule performance index · 1.02CPI1.01Cost performance index · 1.01

Health dimensions

On track

Last update: 2026-10-2615 Jumada I 1448 AH · Up to date

Deliverables

⁦7⁩ of ⁦9⁩ due deliverables accepted on time (⁦78%⁩)

Next milestones

  • Testing & acceptance complete2027-03-0526 Ramadan 1448 AH
  • Final handover2027-04-3023 Dhuʻl-Qiʻdah 1448 AH

Top risks

  • None

Open impediments

  • None

Decisions and changes waiting

  • None

Copilot summary

The scope holds 1 project with a budget of SAR 96M: 1 on track and 0 red or critical. Weighted progress is 58% against 57% planned, spend SAR 55.1M, and EAC SAR 95.1M (SAR 1M under).

No project is more than a month behind baseline.

Saudi Contractors Authority · prepared by Eng. Mishari K. Al-Otaibi in MunjazInternal

Status: On track ·Project page