Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-010On track4ExecutionConstruction

Solar Power for SCA Buildings & Centres

Add to watchlist

6 MW of rooftop and carport solar across 14 SCA buildings and centres, the largest a ground array at the Tabuk site.

Budget (BAC)

SAR 96M

Actual cost

SAR 55.1M

⁦57%⁩ of budget

Progress

⁦58%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 95.1M

SPI · CPI

1.02Schedule performance index · 1.021.01Cost performance index · 1.01

Forecast finish

⁦2027-04-22⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure26 February 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate1 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate2 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate6 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate26 February 2027Closure · Not startedClosure · Not started

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Form no.
SCA-PMO-F08
Template edition
1.1
Version
V1
Form date
⁦2026-05-22⁩
Hijri
5 Dhuʻl-Hijjah 1447 AH
ApprovedCRT-010-05Site works & excavation

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-010
Project
Solar Power for SCA Buildings & Centres
Portfolio
Building Rehabilitation & Sustainability Portfolio
Sector
Corporate Support Sector
Sponsor
Eng. Turki A. Al-Anazi
Project manager
Eng. Mishari K. Al-Otaibi

1The deliverableAuto-filled

DeliverableAuto-filled
Site works & excavation
DescriptionAuto-filled
A contractual output tied to its WBS work package.
OwnerAuto-filled
Eng. Turki A. Al-Anazi
VersionAuto-filled
V1
Weight in the projectAuto-filled
⁦13%⁩
DueAuto-filled
⁦2026-02-16⁩

2Evidence of completionAuto-filled

FileVersionByDate
PRJ-2026-010_3.1_v1.pdfV1Eng. Turki A. Al-Anazi⁦2026-01-14⁩

3Inspection and acceptance criteria

CriterionResult
Matches the approved scope of workMet
Quality review with no major findingsMet
Evidence attached and signed by the ownerMet
Met3 of 3
InspectorAuto-filled
Eng. Bandar M. Al-Shammari
Accepted byAuto-filled
Eng. Turki A. Al-Anazi
Acceptance note
Inspected and accepted against the approved acceptance criteria.

4Financial linkAuto-filled

Contract milestoneAuto-filled
Build complete
ContractAuto-filled
CTR-2025-005
Payment certificateAuto-filled
Linked when the certificate is raised
Payment against itAuto-filled
—

Approval logChain: Deliverable acceptance & certificate · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Turki A. Al-AnaziHead, Qualification & Training SectorSubmitted—⁦2026-01-14⁩ 09:18
2Evidence against the acceptance criteriaMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2026-01-15⁩ 13:22
3Inspection & technical acceptance — ownerTechnical acceptanceEng. Turki A. Al-AnaziProject ownerOn behalf of Eng. Bandar M. Al-ShammariApprovedInspected and accepted against the approved acceptance criteria.⁦2026-01-20⁩ 14:29
4Deliverable matched to the contract lineFinancial approvalMazen A. Al-HazmiProcurement & contractsApproved—⁦2026-01-22⁩ 10:13
5Certificate linked to the payment certificateFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2026-01-25⁩ 11:50

Signatures

Evidence against the acceptance criteria

Ghada A. Al-Shahrani

Approved⁦2026-01-15⁩

Inspection & technical acceptance — owner

Eng. Turki A. Al-Anazi

Approved⁦2026-01-20⁩

Deliverable matched to the contract line

Mazen A. Al-Hazmi

Approved⁦2026-01-22⁩

Certificate linked to the payment certificate

Munirah A. Al-Khalidi

Approved⁦2026-01-25⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F08 · version V1

Deliverable completion certificate

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Deliverable acceptance & certificate · version ⁦1⁩

Submitted by Eng. Turki A. Al-Anazi on ⁦2026-01-14⁩

  1. Methodology review

    Evidence against the acceptance criteria

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2026-01-15⁩ at ⁦13:22⁩

  2. Technical acceptance

    Inspection & technical acceptance — owner

    Eng. Bandar M. Al-Shammari · Project owner

    Approved · ⁦2026-01-20⁩ at ⁦14:29⁩ · On behalf of Eng. Bandar M. Al-Shammari (Eng. Turki A. Al-Anazi)

    Inspected and accepted against the approved acceptance criteria.

  3. Financial approval

    Deliverable matched to the contract line

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2026-01-22⁩ at ⁦10:13⁩

  4. Financial approval

    Certificate linked to the payment certificate

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2026-01-25⁩ at ⁦11:50⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2026-01-14⁩

    PRJ-2026-010_3.1_v1.pdf

    Eng. Turki A. Al-Anazi

Only one version so far.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close