1.02Schedule performance index · 1.021.01Cost performance index · 1.01
Forecast finish
2027-04-22
On baseline
Execution·Stage 4 of 5
Next gate:Closure26 February 2027
Pre-start · CompletePre-start · Complete
Gate into «Initiation»DecisionGoDate1 January 2025Initiation · CompleteInitiation · Complete
Gate into «Planning»DecisionConditional goDate2 March 2025Planning · CompletePlanning · Complete
Gate into «Execution»DecisionGoDate6 July 2025Execution · Current stageExecution · Current stage
Gate into «Closure»DecisionNot held yetDate26 February 2027Closure · Not startedClosure · Not started
Schedule & Gantt
The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.
Finish-date drift
0 days vs approved
Baseline (original = approved) · Current forecast2027-04-30
By earned schedule2028-03-02
Critical activities
1
of 7 open activities
Late activities
4
past their baseline finish
Schedule performance
0.67
earned ÷ planned value
Next milestone
in 128 days
Testing & acceptance complete
Layers
Compare with
Expand allCollapse all
ActivityOwnerForecast finishProgress
2025
2026
2027
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Today
2027-04-3058%
Solar Power for SCA Buildings & CentresPlanned: 2025-03-02 → 2027-04-30Forecast: 2025-03-02 → 2027-04-30Float: 0d