PRJ-2026-016At risk4ExecutionWaterfall

Contracting Sector Information Centre & Data Governance

Add to watchlist

Apply NDMO policies, build one master register of contractors, members and projects, and publish sector indicators regularly.

Budget (BAC)

SAR 21.5M

Actual cost

SAR 14M

⁦65%⁩ of budget

Progress

⁦62%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 22.6M

SAR +1.1M

SPI · CPI

0.89Schedule performance index · 0.890.95Cost performance index · 0.95

Forecast finish

⁦2027-01-18⁩

18 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure20 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 June 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 August 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate24 October 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate20 November 2026Closure · Not startedClosure · Not started

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to work20.9M⁦16⁩ elements
Unallocated contingency645KSAR 1.1M
Budget at completion21.5MPRJ-2026-016
Weighted progress⁦62%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSAR MActualSAR MLinksDeliverables
Project531⁦2025-08-03⁩⁦2027-01-16⁩⁦62%⁩20.8614.03—
1
Phase178⁦2025-08-03⁩⁦2026-01-28⁩⁦100%⁩1.671.81—
1.1
WBS element109⁦2025-08-03⁩⁦2025-11-20⁩⁦100%⁩0.830.910 / 1
1.2
WBS element110⁦2025-10-10⁩⁦2026-01-28⁩⁦100%⁩0.830.911 / 2
2
Phase177⁦2025-12-18⁩⁦2026-06-13⁩⁦100%⁩3.553.85—
2.1
WBS element109⁦2025-12-18⁩⁦2026-04-06⁩⁦100%⁩1.771.931 / 1
2.2
WBS element109⁦2026-02-24⁩⁦2026-06-13⁩⁦100%⁩1.771.931 / 2
3
Phase201⁦2026-04-26⁩⁦2026-11-13⁩⁦92%⁩8.348.37—
3.1
WBS element110⁦2026-05-03⁩⁦2026-08-21⁩⁦100%⁩2.783.021 / 1
3.2
WBS element107⁦2026-07-11⁩⁦2026-10-26⁩⁦100%⁩2.783.021 / 1
3.3
WBS element201⁦2026-04-26⁩⁦2026-11-13⁩⁦77%⁩2.782.331 / 2
4
Phase42⁦2026-11-03⁩⁦2026-12-15⁩⁦0%⁩4.17——
4.1
WBS element26⁦2026-11-03⁩⁦2026-11-29⁩⁦0%⁩2.09—1 / 1
4.2
WBS element26⁦2026-11-19⁩⁦2026-12-15⁩⁦0%⁩2.09—1 / 2
5
Phase42⁦2026-12-05⁩⁦2027-01-16⁩⁦0%⁩3.13——
5.1
WBS element26⁦2026-12-05⁩⁦2026-12-31⁩⁦0%⁩1.56—1 / 1
5.2
WBS element26⁦2026-12-21⁩⁦2027-01-16⁩⁦0%⁩1.56—1 / 1
Total⁦62%⁩20.8614.03