Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-021On track3PlanningConstruction

Asir Vocational Qualification Centre

Add to watchlist

A 120,000 m² regional training and skills-test centre in Abha serving Asir, Jazan, Najran and Al-Baha.

Budget (BAC)

SAR 520M

Actual cost

SAR 10.4M

⁦2%⁩ of budget

Progress

⁦2%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 520M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-12-31⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution12 September 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 February 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 April 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate12 September 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Project status card

One page for the periodic update, to print or export and send to the committee and the sponsor.

Issue schedulePeriodic update cards

Shown by your permissionsProject Management Office: 1 project — everything in your scope

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Project status card

28 October 2026 · 17 Jumada I 1448 AH

Asir Vocational Qualification Centre

PRJ-2026-021 · Corporate Support Sector · Strategic · WP-2026-021

On track3PlanningProject manager: Eng. Ibrahim A. Al-Ghamdi · Sponsor: Eng. Turki A. Al-Anazi
Progress
⁦2%⁩ / ⁦2%⁩
SPI · CPI
1.00 · 1.00
Spend
SAR 10.4M / SAR 520M
Estimate at completion
SAR 520M

Schedule

On plan⁦2%⁩

Planned to date ⁦2%⁩

Forecast finish: 2028-12-3115 Shaʻban 1450 AH · On time

SPI1.00Schedule performance index · 1.00CPI1.00Cost performance index · 1.00

Health dimensions

On track

Last update: 2026-10-2312 Jumada I 1448 AH · Up to date

Deliverables

⁦1⁩ of ⁦1⁩ due deliverables accepted on time (⁦100%⁩)

Next milestones

  • Project plan approved2027-02-169 Ramadan 1448 AH
  • Designs approved2027-07-0429 Muharram 1449 AH
  • Build complete2028-01-2730 Shaʻban 1449 AH
  • Testing & acceptance complete2028-08-2130 Rabiʻ I 1450 AH

Top risks

  • Tender prices 18% above the engineer’s estimate15

Open impediments

  • None

Decisions and changes waiting

  • None

Copilot summary

The scope holds 1 project with a budget of SAR 520M: 1 on track and 0 red or critical. Weighted progress is 2% against 2% planned, spend SAR 10.4M, and EAC SAR 520M (SAR 0M under).

No project is more than a month behind baseline.

Saudi Contractors Authority · prepared by Eng. Ibrahim A. Al-Ghamdi in MunjazInternal

Status: On track ·Project page