Project status card
28 October 2026 · 17 Jumada I 1448 AH
Asir Vocational Qualification Centre
PRJ-2026-021 · Corporate Support Sector · Strategic · WP-2026-021
- Progress
- 2% / 2%
- SPI · CPI
- 1.00 · 1.00
- Spend
- SAR 10.4M / SAR 520M
- Estimate at completion
- SAR 520M
Schedule
Planned to date 2%
Forecast finish: 2028-12-3115 Shaʻban 1450 AH · On time
SPI1.00Schedule performance index · 1.00CPI1.00Cost performance index · 1.00Health dimensions
Last update: 2026-10-2312 Jumada I 1448 AH · Up to date
Deliverables
1 of 1 due deliverables accepted on time (100%)
Next milestones
- Project plan approved2027-02-169 Ramadan 1448 AH
- Designs approved2027-07-0429 Muharram 1449 AH
- Build complete2028-01-2730 Shaʻban 1449 AH
- Testing & acceptance complete2028-08-2130 Rabiʻ I 1450 AH
Top risks
- Tender prices 18% above the engineer’s estimate15
Open impediments
- None
Decisions and changes waiting
- None
Copilot summary
The scope holds 1 project with a budget of SAR 520M: 1 on track and 0 red or critical. Weighted progress is 2% against 2% planned, spend SAR 10.4M, and EAC SAR 520M (SAR 0M under).
No project is more than a month behind baseline.