PRJ-2026-021On track3PlanningConstruction

Asir Vocational Qualification Centre

Add to watchlist

A 120,000 m² regional training and skills-test centre in Abha serving Asir, Jazan, Najran and Al-Baha.

Budget (BAC)

SAR 520M

Actual cost

SAR 10.4M

⁦2%⁩ of budget

Progress

⁦2%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 520M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-12-31⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution12 September 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 February 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 April 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate12 September 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
Fields required by the project’s stage (Planning): 15 fields required now.Field settings

Saudi Contractors Authority

Project charter

Asir Vocational Qualification Centre

APPROVEDV2Approved ⁦2026-04-03⁩

1Project identity

Required at this stage
Project name
Asir Vocational Qualification Centre
Project code
PRJ-2026-021
Project sponsor
Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziHead, Qualification & Training SectorP-010t.alanazi@sca.sa
Project manager
Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@sca.sa
Project owner
Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & PremisesP-013b.alshammari@sca.sa
Portfolio & programme
Headquarters & Regional Centres PortfolioHeadquarters & Major Qualification Centres Programme
Type & methodology
Infrastructure · Construction
Current phase
3Planning

2Background & rationale

Required at this stage

A ⁦120,000⁩ m² regional training and skills-test centre in Abha serving Asir, Jazan, Najran and Al-Baha.

3Objectives

Required at this stage
  1. 1SCA services and programmes in every region

4Scope

Required at this stage

In scope

  • A ⁦120,000⁩ m² regional training and skills-test centre in Abha serving Asir, Jazan, Najran and Al-Baha.
  • Saudi Building Code compliance
  • An approved plan to keep contractor services and training running during the works

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

5High-level requirements

Required at this stage
  1. 1Saudi Building Code compliance
  2. 2An approved plan to keep contractor services and training running during the works
  3. 3Civil-defence requirements

6Deliverables

Required at this stage
1Project management plan⁦2026-05-15⁩
2Main deliverable — stage 1⁦2027-08-29⁩
3Main deliverable — final stage⁦2028-08-13⁩
4Final report⁦2028-12-31⁩

7Key milestones

Required at this stage
  1. Charter approved⁦2026-04-03⁩
  2. Contract signed⁦2026-09-12⁩
  3. 50% of works complete⁦2027-08-29⁩
  4. Provisional acceptance⁦2028-10-12⁩
  5. Closure⁦2028-12-31⁩

8Budget

Required at this stage
  • Main contract⁦72.0%⁩374.4M
  • Supervision & consulting⁦14.0%⁩72.8M
  • Internal team⁦9.0%⁩46.8M
  • Contingency reserve (⁦5%⁩)⁦5.0%⁩26M
The owning sector’s approved budgetTotal520M

9Timeline

Required at this stage
Start
2026-04-0517 Shawwal 1447 AH
Baseline finish
2028-12-3115 Shaʻban 1450 AH
Duration
⁦33⁩ months

10Key risks

Required at this stage
  • HighTender prices ⁦18%⁩ above the engineer’s estimate

11Constraints

Required at this stage
  • Stay within the approved budget
  • Comply with the Government Tenders & Procurement Law

12Assumptions

Required at this stage
  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

13Stakeholders

Required at this stage
  • Project sponsorDecisions and funding
  • Project ownerAccepts deliverables, owns benefits
  • Project Management Office (PMO)Governance and compliance

14Success criteria

Required at this stage
  1. 1Delivered within the approved budget
  2. 2On the approved date ⁦±5%⁩
  3. 3Target benefits within ⁦12⁩ months

15Governance structure

Required at this stage
  • Change Control BoardApproves scope, cost and schedule changesWeekly
  • PMO CommitteeMethodology compliance, data quality, stage gatesFortnightly
  • Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly
Version V2 · ⁦4⁩ of ⁦4⁩ signaturesInternal — not for circulation outside the Board