PRJ-2026-021On track3PlanningConstruction
Asir Vocational Qualification Centre
Add to watchlistA 120,000 m² regional training and skills-test centre in Abha serving Asir, Jazan, Najran and Al-Baha.
Project managerEng. Ibrahim A. Al-GhamdiProject sponsorEng. Turki A. Al-AnaziProgrammeHeadquarters & Major Qualification Centres Programme
Budget (BAC)
SAR 520M
Actual cost
SAR 10.4M
2% of budget
Progress
2%Awaiting acceptance 0%
Estimate at completion
SAR 520M
SPI · CPI
1.00Schedule performance index · 1.001.00Cost performance index · 1.00
Forecast finish
2028-12-31
On baseline
PlanningStage 3 of 5
Next gate:Execution12 September 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate4 February 2026Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate5 April 2026Planning · Current stagePlanning · Current stage
- Gate into «Execution»DecisionNot held yetDate12 September 2026Execution · Not startedExecution · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
Periodic update cards
Filled by the project manager every period — progress, status, risks and support requested — prefilled from the previous card and the live data, then approved.
Periodic update cards
| Period | Status | Progress | Current step | Date |
|---|---|---|---|---|
| October 2026UPD-021-2026-10 | Draft | 2% | — | 2026-10-26 |
| September 2026UPD-021-2026-09 | Approved | 0% | — | 2026-10-02 |
| August 2026UPD-021-2026-08 | Approved | 0% | — | 2026-09-02 |