Asir Vocational Qualification Centre
Add to watchlistA 120,000 m² regional training and skills-test centre in Abha serving Asir, Jazan, Najran and Al-Baha.
Budget (BAC)
Actual cost
2% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
PlanningStage 3 of 5
Next gate:Execution12 September 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate4 February 2026Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate5 April 2026Planning · Current stagePlanning · Current stage
- Gate into «Execution»DecisionNot held yetDate12 September 2026Execution · Not startedExecution · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
Project lifecycle and its gates
Current phase: Planning. Pick a gate on the track to review it.
- Gate into «Initiation»DecisionGoDate4 February 2026All criteria and required documents met.Pre-startComplete
- Gate into «Planning»DecisionGoDate5 April 2026All criteria and required documents met.InitiationComplete
- Gate into «Execution»DecisionNot held yetDate12 September 2026PlanningCurrent stageCurrent stage
- Gate into «Closure»DecisionNot held yet4ExecutionNot started
- 5ClosureNot started
What each stage requires
The documents and approvals each gate asks for before the next stage.
Planning gate — plan and baseline approved
Gate readiness
Meets the pass mark
Automated control: no move until the criteria are met
- 2 mandatory checklist items open
- 1 required document not approved
Checklist
4 of 6 done
- Project management plan: schedule, deliverables, risks, communication, quality and benefitsMandatory
- Deliverables defined with weights that sum to 100%Mandatory
- Schedule and baseline approved and lockedMandatory
- Approved budget and expected commitmentsMandatory
- Finance and procurement sign-off where money or a contract is involvedMandatory
- Initial risk register
Required documents
3 of 4 approved
- Project management planNot submitted
- Approved baselineApproved · V1
- Deliverables register with weightsApproved · V1
- Contract or purchase orderApproved · V1
Criteria and score
Go from 75, conditional from 60; a mandatory criterion is met from 70.
Schedule realismweight 30%Met
Awaiting evidence from the project team.
Cost estimate completenessweight 30%Met
Awaiting evidence from the project team.
Deliverables and acceptance criteria clearweight 25%Met
Awaiting evidence from the project team.
Quality of the risk planweight 15%
Awaiting evidence from the project team.
Approvers
Projects Steering Committee
- Dr. Abdullah S. Al-QahtaniSteering Committee chairVote pending
- Eng. Turki A. Al-AnaziProject sponsorVote pending
- Dr. Noura M. Al-OtaibiPMO directorVote pending
- Munirah A. Al-KhalidiFinance & procurementVote pending