Asir Vocational Qualification Centre
Add to watchlistA 120,000 m² regional training and skills-test centre in Abha serving Asir, Jazan, Najran and Al-Baha.
Budget (BAC)
Actual cost
2% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
PlanningStage 3 of 5
Next gate:Execution12 September 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate4 February 2026Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate5 April 2026Planning · Current stagePlanning · Current stage
- Gate into «Execution»DecisionNot held yetDate12 September 2026Execution · Not startedExecution · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
Scope statementRequired at this stage
What the project delivers, what it does not, and when a deliverable counts as accepted.
A 120,000 m² regional training and skills-test centre in Abha serving Asir, Jazan, Najran and Al-Baha.
In scope
- A 120,000 m² regional training and skills-test centre in Abha serving Asir, Jazan, Najran and Al-Baha.
- Saudi Building Code compliance
- An approved plan to keep contractor services and training running during the works
Out of scope
- Operation and maintenance after the warranty period
- Work outside the approved site or system boundary
Acceptance criteria
- Main deliverable — stage 1Meets the approved specification, signed off by the project owner
- Main deliverable — final stageMeets the approved specification, signed off by the project owner
Scope baselineRequired at this stage
Every approved change creates a new baseline
- 1
SB-1Current2026-05-23
Baseline approved at the planning gate
Budget520MFinish2028-12-31
Requirements registerRequired at this stage
6 requirements of five kinds, with the trace status of each
By type
- Business1
- Functional1
- Technical1
- Regulatory2
- Security1
Fully traced
0%
0/6 · linked to a deliverable, task and test
Test passed
0%
0/6 · test result is a pass
Accepted
0%
0/6 · signed off by the business owner
Display options
| REQ-021-01 | Reach the target number of training & test halls | Business | Must | Approved | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & PremisesP-013b.alshammari@sca.sa | SB-1 | |
| REQ-021-02 | Meet the approved technical specs | Technical | Must | Approved | Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@sca.sa | SB-1 | |
| REQ-021-03 | Training and contractor service continue during the works | Functional | Must | Approved | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & PremisesP-013b.alshammari@sca.sa | SB-1 | |
| REQ-021-04 | Saudi Building Code | Regulatory | Should | Approved | Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@sca.sa | SB-1 | |
| REQ-021-05 | Civil-defence requirements | Regulatory | Should | Approved | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & PremisesP-013b.alshammari@sca.sa | SB-1 | |
| REQ-021-06 | Site and systems security | Security | Could | Approved | Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@sca.sa | SB-1 |
Traceability matrixRequired from Execution
Requirement → deliverable → task → test → acceptance. 6 requirements have a gap.