PRJ-2026-021On track3PlanningConstruction

Asir Vocational Qualification Centre

Add to watchlist

A 120,000 m² regional training and skills-test centre in Abha serving Asir, Jazan, Najran and Al-Baha.

Budget (BAC)

SAR 520M

Actual cost

SAR 10.4M

⁦2%⁩ of budget

Progress

⁦2%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 520M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-12-31⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution12 September 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 February 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 April 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate12 September 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Project weight

The weight and the relative weight in the portfolio

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Approval

Project weight

The weight and the relative weight in the portfolio

Form no.
SCA-PMO-F03
Template edition
1.0
Version
V2
Form date
⁦2026-09-16⁩
Hijri
5 Rabiʻ II 1448 AH
ApprovedPRJ-2026-021Asir Vocational Qualification Centre

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-021
Project
Asir Vocational Qualification Centre
Portfolio
Headquarters & Regional Centres Portfolio
Sector
Corporate Support Sector
Sponsor
Eng. Turki A. Al-Anazi
Project manager
Eng. Ibrahim A. Al-Ghamdi

1Weight and relative weightAuto-filled

Project weight score

89 of 100

Relative weight in the portfolio

⁦16.3%⁩

Portfolio

Headquarters & Regional Centres Portfolio

8 projects

Its share of the portfolio’s progress

0.3 points of 35.3%

2Weight criteriaAuto-filled

Each criterion is rated 1–5 from the project’s record and multiplied by its approved weight.

CriterionRated fromWeightRatingPoints
Strategic importanceThe project’s strategic value⁦35%⁩428.0
Budget sizeApproved budget (BAC)⁦25%⁩525.0
Impact on contractors & beneficiariesThe project’s alignment score⁦20%⁩520.0
Complexity & riskThe project’s risk score⁦10%⁩36.0
Project classificationThe project’s classification⁦10%⁩510.0
Weight score—⁦100%⁩—89

3Relative weights across the portfolioAuto-filled

Proposed and cancelled projects are left out; suspended ones keep their frozen progress.

ProjectScoreRelative weightProgress
SCA Headquarters, Riyadh100⁦18.3%⁩⁦42%⁩
Asir Vocational Qualification Centre89⁦16.3%⁩⁦2%⁩
Qassim Vocational Qualification Centre88⁦16.1%⁩⁦44%⁩
Arar Vocational Qualification Centre80⁦14.6%⁩⁦33%⁩
Electronic Skills-test Halls — Makkah Region66⁦12.1%⁩⁦2%⁩
Smart Test-hall Proctoring & Access Control62⁦11.3%⁩⁦79%⁩
Secure Enterprise Network62⁦11.3%⁩⁦55%⁩
Unified Operations Centre for Centres & Platforms69Not counted⁦0%⁩
Weighted portfolio progress—⁦100%⁩⁦35.3%⁩

Approval logChain: Project weight approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Ghada A. Al-ShahraniDirector, Qualification Programmes & CapabilitySubmitted—⁦2026-09-16⁩ 11:20
2Weight model complianceMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2026-09-17⁩ 13:04
3Portfolio manager approvalTechnical acceptanceEng. Bandar M. Al-ShammariPortfolio managerApproved—⁦2026-09-22⁩ 14:11

Signatures

Weight model compliance

Ghada A. Al-Shahrani

Approved⁦2026-09-17⁩

Portfolio manager approval

Eng. Bandar M. Al-Shammari

Approved⁦2026-09-22⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F03 · version V2

Project weight

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project weight approval · version ⁦1⁩

Submitted by Ghada A. Al-Shahrani on ⁦2026-09-16⁩

  1. Methodology review

    Weight model compliance

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2026-09-17⁩ at ⁦13:04⁩

  2. Technical acceptance

    Portfolio manager approval

    Eng. Bandar M. Al-Shammari · Portfolio manager

    Approved · ⁦2026-09-22⁩ at ⁦14:11⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2026-09-14⁩

    Classification added at 10; budget cut from 35 to 25 so the building projects do not swamp the portfolio

    Dr. Noura M. Al-Otaibi

  2. V1Approved⁦2025-12-02⁩

    First model: strategic importance, budget, impact, complexity

    Dr. Noura M. Al-Otaibi

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close