Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-022On track3PlanningStage-Gate

Electronic Skills-test Halls — Makkah Region

Add to watchlist

Fit out 180 secure e-test seats with recording and proctoring in Jeddah, Makkah and Taif, co-funded with a partner entity.

Budget (BAC)

SAR 46M

Actual cost

SAR 920K

⁦2%⁩ of budget

Progress

⁦2%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 46M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-03-31⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution7 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 June 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate2 August 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate7 November 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Project status card

One page for the periodic update, to print or export and send to the committee and the sponsor.

Issue schedulePeriodic update cards

Shown by your permissionsProject Management Office: 1 project — everything in your scope

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Project status card

28 October 2026 · 17 Jumada I 1448 AH

Electronic Skills-test Halls — Makkah Region

PRJ-2026-022 · Digital Transformation Sector · External · WP-2026-022

On track3PlanningProject manager: Eng. Yasser M. Al-Zahrani · Sponsor: Eng. Majed S. Al-Rasheed
Progress
⁦2%⁩ / ⁦2%⁩
SPI · CPI
1.00 · 1.00
Spend
SAR 920K / SAR 46M
Estimate at completion
SAR 46M

Schedule

On plan⁦2%⁩

Planned to date ⁦2%⁩

Forecast finish: 2028-03-315 Dhuʻl-Qiʻdah 1449 AH · On time

SPI1.00Schedule performance index · 1.00CPI1.00Cost performance index · 1.00

Health dimensions

On track

Last update: 2026-10-187 Jumada I 1448 AH · Up to date

Deliverables

⁦1⁩ of ⁦1⁩ due deliverables accepted on time (⁦100%⁩)

Next milestones

  • Project plan approved2027-01-0830 Rajab 1448 AH
  • Designs approved2027-04-081 Dhuʻl-Qiʻdah 1448 AH
  • Build complete2027-08-2119 Rabiʻ I 1449 AH
  • Testing & acceptance complete2028-01-036 Shaʻban 1449 AH

Top risks

  • Privacy requirements for e-test recordings under the Personal Data Protection Law9

Open impediments

  • None

Decisions and changes waiting

  • None

Copilot summary

The scope holds 1 project with a budget of SAR 46M: 1 on track and 0 red or critical. Weighted progress is 2% against 2% planned, spend SAR 0.9M, and EAC SAR 46M (SAR 0M under).

No project is more than a month behind baseline.

Saudi Contractors Authority · prepared by Eng. Yasser M. Al-Zahrani in MunjazInternal

Status: On track ·Project page

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close