Electronic Skills-test Halls — Makkah Region
Add to watchlistFit out 180 secure e-test seats with recording and proctoring in Jeddah, Makkah and Taif, co-funded with a partner entity.
Budget (BAC)
Actual cost
2% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
PlanningStage 3 of 5
Next gate:Execution7 November 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate3 June 2026Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate2 August 2026Planning · Current stagePlanning · Current stage
- Gate into «Execution»DecisionNot held yetDate7 November 2026Execution · Not startedExecution · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2026-12-05 | 2027-01-08 | +34 days | Eng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@sca.sa | At risk | 0 | Not requested |
| Designs approvedMS-G2 | Project | 2027-03-12 | 2027-04-08 | +27 days | Eng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@sca.sa | At risk | 0 | Not requested |
| Build completeMS-G3 | Contractual | 2027-08-03 | 2027-08-21 | +18 days | Eng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@sca.sa | On track | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2027-12-26 | 2028-01-03 | +8 days | Eng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@sca.sa | On track | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2028-03-31 | 2028-04-02 | +2 days | Eng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@sca.sa | On track | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
2%Awaiting acceptance
0%Not handed in
98%Deliverable flow
Display options
| Project plan & baseline022-D1 | 2% | CRT-022-01 | Approved | Eng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@sca.sa | Eng. Bandar M. Al-Shammari | 2026-10-18 | V1 | 3 of 3 |
| Monitoring & reporting022-D2 | 3% | — | Draft | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & PremisesP-013b.alshammari@sca.sa | Eng. Bandar M. Al-Shammari | 2026-12-05 | V0 | 0 of 3 |
| Detailed design022-D3 | 6% | — | Draft | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & PremisesP-013b.alshammari@sca.sa | Eng. Bandar M. Al-Shammari | 2027-01-22 | V0 | 0 of 3 |
| Permits & approvals022-D4 | 6% | — | Draft | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedHead, Digital Transformation SectorP-011m.alrasheed@sca.sa | Eng. Bandar M. Al-Shammari | 2027-03-12 | V0 | 0 of 3 |
| Site works & excavation022-D5 | 13% | — | Draft | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedHead, Digital Transformation SectorP-011m.alrasheed@sca.sa | Eng. Bandar M. Al-Shammari | 2027-04-29 | V0 | 0 of 3 |
| Structure022-D6 | 13% | — | Draft | Eng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@sca.sa | Eng. Bandar M. Al-Shammari | 2027-06-16 | V0 | 0 of 3 |
| Finishes022-D7 | 13% | — | Draft | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & PremisesP-013b.alshammari@sca.sa | Eng. Bandar M. Al-Shammari | 2027-08-03 | V0 | 0 of 3 |
| Supply022-D8 | 10% | — | Draft | Eng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@sca.sa | Eng. Bandar M. Al-Shammari | 2027-09-20 | V0 | 0 of 3 |
| Installation022-D9 | 10% | — | Draft | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & PremisesP-013b.alshammari@sca.sa | Eng. Bandar M. Al-Shammari | 2027-11-07 | V0 | 0 of 3 |
| Testing & commissioning022-D10 | 10% | — | Draft | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedHead, Digital Transformation SectorP-011m.alrasheed@sca.sa | Eng. Bandar M. Al-Shammari | 2027-12-26 | V0 | 0 of 3 |
| Provisional acceptance022-D11 | 7% | — | Draft | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & PremisesP-013b.alshammari@sca.sa | Eng. Bandar M. Al-Shammari | 2028-02-12 | V0 | 0 of 3 |
| Final acceptance022-D12 | 7% | — | Draft | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedHead, Digital Transformation SectorP-011m.alrasheed@sca.sa | Eng. Bandar M. Al-Shammari | 2028-03-31 | V0 | 0 of 3 |
| Total · 12 | 100% |