Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-029On track3PlanningWaterfall

SCA Academy — Learning Platform & Professional Tracks

Add to watchlist

A learning management platform for qualification programmes and accredited professional tracks for sector workers, with accredited training partners.

Budget (BAC)

SAR 7.5M

Actual cost

SAR 300K

⁦4%⁩ of budget

Progress

⁦4%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 7.5M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2027-12-31⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution4 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate17 June 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate16 August 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate4 November 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Project status card

One page for the periodic update, to print or export and send to the committee and the sponsor.

Issue schedulePeriodic update cards

Shown by your permissionsProject Management Office: 1 project — everything in your scope

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Project status card

28 October 2026 · 17 Jumada I 1448 AH

SCA Academy — Learning Platform & Professional Tracks

PRJ-2026-029 · Qualification & Training Sector · Strategic · WP-2026-029

On track3PlanningProject manager: Ghada A. Al-Shahrani · Sponsor: Sarah A. Al-Qarni
Progress
⁦4%⁩ / ⁦4%⁩
SPI · CPI
1.00 · 1.00
Spend
SAR 300K / SAR 7.5M
Estimate at completion
SAR 7.5M

Schedule

On plan⁦4%⁩

Planned to date ⁦4%⁩

Forecast finish: 2027-12-313 Shaʻban 1449 AH · On time

SPI1.00Schedule performance index · 1.00CPI1.00Cost performance index · 1.00

Health dimensions

On track

Last update: 2026-10-154 Jumada I 1448 AH · Up to date

Deliverables

⁦1⁩ of ⁦1⁩ due deliverables accepted on time (⁦100%⁩)

Next milestones

  • Project plan approved2027-01-0527 Rajab 1448 AH
  • Designs approved2027-04-0124 Shawwal 1448 AH
  • Build complete2027-08-086 Rabiʻ I 1449 AH
  • Testing & acceptance complete2027-11-023 Jumada II 1449 AH

Top risks

  • None

Open impediments

  • None

Decisions and changes waiting

  • None

Copilot summary

The scope holds 1 project with a budget of SAR 7.5M: 1 on track and 0 red or critical. Weighted progress is 4% against 4% planned, spend SAR 0.3M, and EAC SAR 7.5M (SAR 0M under).

No project is more than a month behind baseline.

Saudi Contractors Authority · prepared by Ghada A. Al-Shahrani in MunjazInternal

Status: On track ·Project page

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close