SCA Academy — Learning Platform & Professional Tracks
Add to watchlistA learning management platform for qualification programmes and accredited professional tracks for sector workers, with accredited training partners.
Budget (BAC)
Actual cost
4% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
PlanningStage 3 of 5
Next gate:Execution4 November 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionConditional goDate17 June 2026Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate16 August 2026Planning · Current stagePlanning · Current stage
- Gate into «Execution»DecisionNot held yetDate4 November 2026Execution · Not startedExecution · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
Scope statementRequired at this stage
What the project delivers, what it does not, and when a deliverable counts as accepted.
A learning management platform for qualification programmes and accredited professional tracks for sector workers, with accredited training partners.
In scope
- A learning management platform for qualification programmes and accredited professional tracks for sector workers, with accredited training partners.
- Service procedure manual
- Beneficiary satisfaction measures
Out of scope
- Operation and maintenance after the warranty period
- Work outside the approved site or system boundary
Acceptance criteria
- Main deliverable — stage 1Meets the approved specification, signed off by the project owner
- Main deliverable — final stageMeets the approved specification, signed off by the project owner
Scope baselineRequired at this stage
Every approved change creates a new baseline
- 1
SB-1Current2026-09-09
Baseline approved at the planning gate
Budget7.5MFinish2027-12-31
Requirements registerRequired at this stage
6 requirements of five kinds, with the trace status of each
By type
- Business1
- Functional2
- Technical1
- Regulatory1
- Security1
Fully traced
0%
0/6 · linked to a deliverable, task and test
Test passed
0%
0/6 · test result is a pass
Accepted
0%
0/6 · signed off by the business owner
Display options
| REQ-029-01 | Shorter service time | Business | Must | Approved | Abdulmajeed R. Al-DosariAbdulmajeed R. Al-DosariDirector General, Human ResourcesP-019am.aldosari@sca.sa | SB-1 | |
| REQ-029-02 | A single procedure manual | Functional | Must | Approved | Ghada A. Al-ShahraniGhada A. Al-ShahraniDirector, Qualification Programmes & CapabilityP-029g.alshahrani@sca.sa | SB-1 | |
| REQ-029-03 | Beneficiary satisfaction measures | Functional | Must | Approved | Abdulmajeed R. Al-DosariAbdulmajeed R. Al-DosariDirector General, Human ResourcesP-019am.aldosari@sca.sa | SB-1 | |
| REQ-029-04 | Booking and queue systems | Technical | Should | Approved | Ghada A. Al-ShahraniGhada A. Al-ShahraniDirector, Qualification Programmes & CapabilityP-029g.alshahrani@sca.sa | SB-1 | |
| REQ-029-05 | Service quality standards | Regulatory | Should | Approved | Abdulmajeed R. Al-DosariAbdulmajeed R. Al-DosariDirector General, Human ResourcesP-019am.aldosari@sca.sa | SB-1 | |
| REQ-029-06 | Personal data protection | Security | Could | Approved | Ghada A. Al-ShahraniGhada A. Al-ShahraniDirector, Qualification Programmes & CapabilityP-029g.alshahrani@sca.sa | SB-1 |
Traceability matrixRequired from Execution
Requirement → deliverable → task → test → acceptance. 6 requirements have a gap.