Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-029On track3PlanningWaterfall

SCA Academy — Learning Platform & Professional Tracks

Add to watchlist

A learning management platform for qualification programmes and accredited professional tracks for sector workers, with accredited training partners.

Budget (BAC)

SAR 7.5M

Actual cost

SAR 300K

⁦4%⁩ of budget

Progress

⁦4%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 7.5M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2027-12-31⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution4 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate17 June 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate16 August 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate4 November 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SAR 7.5M split into spent, committed and left, with the estimate at completion

EAC SAR 7.5M
Revised request SAR 7.5M
  • Actual spendSAR 300K
  • Committed, not spentSAR 600K
  • Allotted, uncommittedSAR 6.4M
  • Contingency availableSAR 225K

Budget

EstimatedManualFrom the project proposal — not from the finance systemthe proposal’s cost before approval
SAR 7.5M
Original budgetwhen the first baseline was approved
SAR 7.5M
Approved budgetafter approved change requests
SAR 7.5M
Current budgetavailable to spend now
SAR 7.5M
Revised budgetif the pending changes are approved
SAR 7.5M

Commitments

CommitmentsSyncedFrom the nightly finance-system syncsigned contracts and purchase orders
SAR 900K
Contracts0 active contracts
SAR 0
Purchase orders⁦1⁩ order
SAR 900K
Remaining budgetapproved less actual
SAR 7.2M

Spend & outlook

Actual costSyncedFrom the nightly finance-system syncincluding accruals
SAR 300K
Accrualswork done, not yet invoiced
SAR 12K
Estimate at completionManualThe project manager’s estimate — not from the finance systemthe PM’s bottom-up forecast
SAR 7.5M
ContingencySAR 150K drawn of SAR 375K
SAR 225K

Estimated vs approved budget

What the project proposal estimated before approval, against today’s approved budget and the estimate at completion

EstimatedSAR 7.5M
ApprovedSAR 7.5M
Estimate at completionSAR 7.5M
Approved equals the estimate
The estimate at completion is SAR 0 (⁦0.0%⁩) below the estimate

From proposal DMD-2026-006 in the annual work plan — its estimated cost

ERP link — data readiness

The link keys are ready for the finance-system sync; Munjaz follows the project and does not replace the accounting system

⁦4⁩ of ⁦4⁩ fields ready
  • Cost centreCC-51029
  • WBS elements⁦5⁩ elements · P-2026-029.01 …
  • Purchase orders⁦1⁩ synced · ⁦0⁩ manual
  • Invoices & certificatesNo certificates
Last sync⁦2026-10-28⁩ · 06:00 · succeededNext tonight at 02:00

Where each figure comes from

  • EstimatedManualFrom the project proposal — not from the finance system
  • CommitmentsSyncedFrom the nightly finance-system sync
  • Actual costSyncedFrom the nightly finance-system sync
  • Estimate at completionManualThe project manager’s estimate — not from the finance system

Once the link is live, synced figures are read from the finance system; manual updates stay available to the same roles and are logged.

Purchase-order register

Manual edit log

Every manual update — who, when, why and from which source

No manual edits on this project

All its figures come from the finance-system sync. Finance & procurement — and the project manager, for the estimate at completion — can update them by hand.

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SAR 150K drawn of SAR 375K

  • Covering realised delivery risks⁦2026-08-29⁩SAR 150K

Purchase orders

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSAR MCommittedSAR MActualSAR MEACSAR MVarianceSAR MConsumption
1Management & governance0.580.320.300.59⁦−0.00⁩
2Analysis & design1.240.110.001.26⁦−0.02⁩
3Build2.910.250.002.96⁦−0.05⁩
4Testing & acceptance1.460.130.001.48⁦−0.02⁩
5Launch & handover1.090.090.001.11⁦−0.02⁩
Unallocated contingency0.230.000.000.11⁦+0.11⁩
Total7.500.900.307.50⁦+0.00⁩

Budget split

WBS

SAR 7.5M

Budget

  • Management & governanceSAR 582K⁦8%⁩
  • Analysis & designSAR 1.2M⁦16%⁩
  • BuildSAR 2.9M⁦39%⁩
  • Testing & acceptanceSAR 1.5M⁦19%⁩
  • Launch & handoverSAR 1.1M⁦15%⁩
  • Unallocated contingencySAR 225K⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SAR millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative
  • Forecast

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2028-08-23⁩+236

SPI(t) ⁦0.68⁩ against the approved finish ⁦2027-12-31⁩

Planned valuePV
SAR 618K
The value of the work that should be done by today.
PV
Earned valueEV
SAR 300K
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SAR 300K
What has actually been spent on the work done.
AC
Budget at completionBAC
SAR 7.5M
The approved budget for the whole project.
BAC
Cost varianceCV
⁦+0.00⁩ SAR M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−0.32⁩ SAR M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
1.00
Value produced per riyal spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.49
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SAR 7.5M
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SAR 7.2M
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦+0.00⁩ SAR M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
1.00
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSAR 7.5M
  • If the rest goes to planSAR 7.5M
  • At cost and schedule performanceSAR 15.1M
  • The PM’s bottom-up estimateSAR 7.5M
  • The performance needed on the rest is below what has been achieved; the budget holds.

Estimate at completion at that performance

SAR 7.5M

Variance at completion: ⁦+0.00⁩ SAR M

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close