1.00Schedule performance index · 1.001.00Cost performance index · 1.00
Forecast finish
2027-12-31
On baseline
Planning·Stage 3 of 5
Next gate:Execution4 November 2026
Pre-start · CompletePre-start · Complete
Gate into «Initiation»DecisionConditional goDate17 June 2026Initiation · CompleteInitiation · Complete
Gate into «Planning»DecisionGoDate16 August 2026Planning · Current stagePlanning · Current stage
Gate into «Execution»DecisionNot held yetDate4 November 2026Execution · Not startedExecution · Not started
Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
Schedule & Gantt
The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.
Finish-date drift
+27 days vs approved
Baseline (original = approved)2027-12-31
Current forecast2028-01-27
By earned schedule2028-08-23
Critical activities
11
of 15 open activities
Late activities
10
past their baseline finish
Schedule performance
0.49
earned ÷ planned value
Next milestone
in 69 days
Project plan approved
Layers
Compare with
Expand allCollapse all
ActivityOwnerForecast finishProgress
2026
2027
2028
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
Today
2028-01-274%
SCA Academy — Learning Platform & Professional TracksPlanned: 2026-08-16 → 2027-12-31Forecast: 2026-08-16 → 2028-01-27Float: 0d
Project plan & baselinePlanned: 2026-08-16 → 2026-10-24Actual: 2026-08-16 → 2026-10-26
2027-01-050%
Monitoring & reportingPlanned: 2026-09-28 → 2026-12-07Forecast: 2026-10-28 → 2027-01-05Float: 0dDrag to change its dates+29
2027-01-050%
Project plan approvedPlanned: 2026-12-07 → 2026-12-07Forecast: 2027-01-05 → 2027-01-05Float: 387dDrag to change its datesProject plan approved