PRJ-2026-030On track5ClosureWaterfall

Enterprise Risk & Business Continuity Framework

Add to watchlist

A framework, policies and a single register for enterprise risk and business continuity, with a risk appetite approved by the board.

Project managerTariq S. Al-YamiProject sponsorDr. Mohammed I. Al-Subaie

Budget (BAC)

SAR 3.6M

Actual cost

SAR 3.5M

⁦96%⁩ of budget

Progress

⁦100%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 3.5M

SPI · CPI

1.00Schedule performance index · 1.001.04Cost performance index · 1.04

Forecast finish

⁦2026-08-31⁩

On baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate8 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate9 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate3 June 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate19 July 2026Closure · Current stageClosure · Current stage

Priority evaluation

Criteria, weights and the P1–P4 result

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Priority evaluation

Criteria, weights and the P1–P4 result

Form no.
SCA-PMO-F02
Template edition
1.3
Version
V4
Form date
⁦2024-10-05⁩
Hijri
2 Rabiʻ II 1446 AH
ApprovedPRJ-2026-030Enterprise Risk & Business Continuity Framework

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-030
Project
Enterprise Risk & Business Continuity Framework
Portfolio
Institutional Excellence & Governance Portfolio
Sector
Strategy & Institutional Excellence Sector
Sponsor
Dr. Mohammed I. Al-Subaie
Project manager
Tariq S. Al-Yami

1The resultAuto-filled

Priority score

63 of 100

Class

P2

60–74

Priority model

Version 4

Class thresholdsAuto-filled

P1 from 75 · P2 from 60 · P3 from 45 · P4 below 45

2Criteria and weightsAuto-filled

Rated 1–5; the cost criteria (risk, complexity, resources) are turned around before weighting.

CriterionWeightRatingPoints
Fit with the SCA strategy⁦20%⁩4.517.5
Value added to the contracting sector⁦12%⁩3.78.1
Financial return & sustainability⁦8%⁩3.34.6
Urgency⁦10%⁩3.35.7
Regulatory requirement⁦10%⁩1.61.5
Risk⁦7%⁩1.46.3
Complexity⁦6%⁩1.35.5
Resource requirement⁦5%⁩1.05.0
Impact on contractors & beneficiaries⁦14%⁩2.86.3
Sustainability impact⁦3%⁩2.00.8
Digital transformation impact⁦5%⁩2.01.3
Total⁦100%⁩—63

Approval logChain: Priority evaluation approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Ghada A. Al-ShahraniDirector, Qualification Programmes & CapabilitySubmitted—⁦2024-10-05⁩ 12:33
2Evaluation checked against the modelMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2024-10-07⁩ 10:07
3Portfolio manager reviewTechnical acceptanceDr. Noura M. Al-OtaibiPortfolio managerApproved—⁦2024-10-08⁩ 11:14
4Class approved — Project Approval CommitteeTechnical acceptanceDr. Noura M. Al-OtaibiProject Approval CommitteeApproved—⁦2024-10-14⁩ 12:21

Signatures

Evaluation checked against the model

Ghada A. Al-Shahrani

Approved⁦2024-10-07⁩

Portfolio manager review

Dr. Noura M. Al-Otaibi

Approved⁦2024-10-08⁩

Class approved — Project Approval Committee

Dr. Noura M. Al-Otaibi

Approved⁦2024-10-14⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F02 · version V4

Priority evaluation

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Priority evaluation approval · version ⁦1⁩

Submitted by Ghada A. Al-Shahrani on ⁦2024-10-05⁩

  1. Methodology review

    Evaluation checked against the model

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2024-10-07⁩ at ⁦10:07⁩

  2. Technical acceptance

    Portfolio manager review

    Dr. Noura M. Al-Otaibi · Portfolio manager

    Approved · ⁦2024-10-08⁩ at ⁦11:14⁩

  3. Technical acceptance

    Class approved — Project Approval Committee

    Dr. Noura M. Al-Otaibi · Project Approval Committee

    Approved · ⁦2024-10-14⁩ at ⁦12:21⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V4ApprovedCurrent⁦2024-10-05⁩

    Evaluated on the approved priority model

    Ghada A. Al-Shahrani

Only one version so far.